Baseline
the projects scope fixed at a specific point in time - for example, the projects scheduled start date
Control systems
Ensure that any changes to the project baseline are conducted in a systematic and thorough manner.
Deliverables
Any measurable, tangible, verifiable outcome, result, or item that must be produced to complete a project or part of a project.
Milestones
Significant event in the project. Ex: a milestone or checkpoint
Project Charter
Document issued by the project initiator or sponsor that formally sanctions the existence of the project and authorizes the project manage to begin applying organizational resources to project activities.
Project closeout
Requires PM’s to consider the types of records and reports they and their clients will require at the completion of the project.
Project scope
Is everything about a project-work content as well as expected outcomes.
Responsibility assignment Matrix (RAM)
To identify team personnel who will be directly responsible for each task in the project’s development, a RAM is developed.
Scope management
Is the function of controlling a project in terms of its goals and objectives through the processes of conceptual development, full definition, execution, and termination.
Scope reporting
Is about the types of information that will be regularly reported, who will receive copies of this information, and how this information will be acquired and disseminated.
Scope statement
The heart of scope management, reflects a project team’s best efforts at creating the documentation and approval of all important project parameters prior to proceeding to the development phase.
Statement of work (SOW)
Detailed narrative description of the work required for a project.
Work authorization
Gives formal go-ahead to commence with the project.
Work breakdown structure (WBS)
Divides the project into its component sub steps in order to begin establishing critical interrelationships among activities.
Work packages
Are defined as WBS elements of the project that are isolated for assignment to “work centers” for accomplishment.