Chapter 9: Budget and Resources Flashcards

1
Q

C9 Budget and Resources: Terms and terminology

A
  • Earned Value Analysis (EVA) - data analysis method to evaluate performance against the performance measurement baseline (scope, schedule, cost baselines)
  • Earned Value Management (EVM) - практика управления scope/schedule/cost с использованием EVA для контроля проекта
  • Benefits Management Plan - explains processes for creating, maximizing, and sustaining the benefits provided by a project or program.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Aggregating cost to create a budget

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Formulas for Earned Value Analysis

A

Выучить хотя бы SV, CV, CPI, SPI и понимать их

  • EV comes first во всех формулах
  • Variance means subtract
  • Index means division
  • If the formula relates to cost, use AC
  • If the formula relates to schedule, use PV
  • For variances interpretation: Negative is bad :( and positive is good :)
  • For indices interpretation: Greater than one is good :) and less than one is bad :(. This only applies to CPI&SPI ! The opposite is true for TCPI !
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Types of Cost

A

2 измерения

  • Вариативность:
    • Variable costs - changes with the amount of production work (e.g. Materials, wages)
    • Fixed costs - do not change as production changes
  • Отнесение к проекту
    • Direct costs - относятся к проекту (team wages, training, travel)
    • Indirect costs - бенефиты нескольким проектам (taxes, fringe benefits)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly