Chapter 9 & 11 Flashcards

1
Q

3 most common project restraints

A
  • Time
  • Money
  • Resources (people, equipment, etc. )
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

3 levels of authority in balancing a project

A
  • Project
  • Business Case
  • Enterprise
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

BALANCING AT THE “PROJECT” LEVEL involves…

A
  1. Re-estimate the Project
  2. Change Task Assignments to Take Advantage of
    Schedule Float
  3. Add People to the Project
  4. Increase Productivity by Using Experts From Within the Firm
  5. Increase Productivity by Using Experts From Outside the
    Firm
  6. Outsourcing the Entire Project or a Significant Portion of it
  7. Crashing the Schedule
  8. Working Overtime
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BALANCING AT THE “BUSINESS CASE” LEVEL

A
  1. Reduce the Product Scope
  2. Fixed-Phase Scheduling
  3. Fast-Tracking
  4. Phased Product Delivery
  5. Do It Twice - Quickly and Correctly
  6. Change the Profit Requirement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

BALANCING AT THE “ENTERPRISE” LEVEL

A
  1. Outsourcing
  2. Phased product delivery
  3. Shifting work to the customer
  4. Reducing the project scope
  5. Using productivity tools
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

BALANCING THE TRADE-OFF

A

• No matter what is done there will always more
good ideas than time and money allows

• Balancing should wait until the end of the planning
phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

• Every PM technique is a

A

communicating technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

• Rules for assigning tasks

A

• Explain the deliverables
• Be clear on the expected level of effort and the due dates
• Let them know of any obstacles they can expect that you
are aware of
• Hand out assignments personally, allowing time for questions and discussion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

INDIVIDUAL STATUS MEETINGS

A
  • Plan to spend time with every team member on a regular basis
  • Open Door Policy
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

• Status meetings provide opportunity to:

A
  • Increase team cohesion

* Keep the team well informed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

• Use open task report (OTR) to…

A

get the status of everything being worked on or recently completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

all about CONTROL DOCUMENTS….

A

• change depending on the project and the industry
• called control documents because they are tools
to maintain control over the product and the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

8 basic components common to every CM process

A
  1. Identification of deliverables
  2. Creation of intermediate deliverables
  3. Stake holder education/modification
  4. Formal acceptance (now we have a control doc)
  5. Recording of change requests
  6. Evaluation of request and recommendations
  7. Ongoing stakeholder evaluation/modification
  8. Formal acceptance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

separate changes into different categories (threshold):

A
  • Lowest threshold - changes that the project team can approve, these changes typically don’t affect cost or schedule (ex. Product improvement)
  • Second threshold - these will affect cost, schedule, or the functionality
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

• Change Board

A

Manage second level threshold changes
• Meet on a regular basis and represent the views of all the
stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

• Members of the Change Board

A
  • Representatives of the project team
  • The customers representative
  • Representatives from groups with related products
  • Representatives from functional management
17
Q

CONFIGURATION MANAGEMENT is…

A

When a change is made it has to be integrated into the project
• Anything that can have versions should use config. mgt.
• Limits the change to control documents and other project deliverables

18
Q

HOW CONFIGURATION MANAGEMENT IS ACCOMPLISHED

A

• Step 1: Identify items/products
• Step 2: Establish control structure (Who will make changes, how, and do you need versions?)
• Step 3: Assign configuration management
responsibility

19
Q

CLOSEOUT REPORTING can include

A
  • The delivery of final product or may be the end of a product development phase
  • It gives finality to the project and presents a learning opportunity