Chapter 7 & 8 Flashcards
STEPS TO CREATING A DETAILED PLAN (8)
- Create project definition (SOW)
- Create a responsibility matrix
- Develop a risk management strategy
- Build a work breakdown structure (WBS)
- Identify task relationships
- Estimate work packages
- Calculate initial schedule
- Assign and level resources
When there is a series of tasks that need to be performed there will be ______________.
sequence constraints
When tasks can be performed at the same time, they are known as __________.
concurrent tasks
Task A must finish before task B can starts is A.K.A
finish to start
Task A must start before task B can start is A.K.A
start to start
Task A must finish before Task B can finish is A.K.A
finish to finish
Building the cost and schedule estimates by starting from the work packages is called
bottom-up estimating.
Productivity can reduce duration by way of
experience
Cost Estimates Come From 4 Sources:
- Labour Estimates
- Equipment Estimates
- Materials Estimates
- Fixed-Price Bids
Steps to CALCULATE INITIAL SCHEDULE:
STEP 1: Forward Pass
STEP 2: Backward Pass
STEP 3: Calculate Float
The path in the project plan (typically shown via the network diagram) that contains all of the tasks with zero or negative float is called the ________ and it’s the _______ path.
- critical path
2. longest path
Two alternative ways to calculate schedule (other than network diagrams) include:
Gantt Charts & Time-Scaled Networks.
RESOURCE LEVELLING is
all about optimizing the use of people and
equipment assigned to a given project.
RESOURCE LEVELLING assumption is:
whenever possible it is most productive to have consistent, continuous use of the fewest resources possible
This is the last step to creating a realistic schedule…
RESOURCE LEVELLING