Chapter 8 The planning process Flashcards

1
Q

Name some important reasons for a good planning of a construction project.

A
  • To set realistic time framework for a project
  • To establish realistic standards and avoid ”wishful thinking”
  • To give a basis for control during the project
  • To monitor preformance in term of output, time and money
  • To review progress and take action whem nesscary
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

2.We talk about different planning programmes at different stages of a project. Name, for the
following stages, some important programmes and mention who is preparing (responsible for) the programme in question:

A

a. Design-stage: projectmaster schedule prepared by: client
b. Tender-stage: pretender programme; contractor
c. Contract-stage: Master programme, target programme, sub-contractors programme, procurement programme, all these are prepared by the contractor and the sub-contractor. The stage programme, short-term programme and as-built programme are prepared by the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Who is preparing (responsible for) a project master programme? Describe briefly the content of such a programme.

A

It is prepared by the client (agent, represantivies or project manager. And it contents: Key dates: start and completion, design, tender and construction dates it shows overall programming and phasing and handover dates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

4.What is a pre-tender programme? Who is usually preparing it? Give some important reasons for a pre-tender planning!

A
  • The contractor is preparing it
  • To identify keydates or gateways at critical stages of the project.
  • To establish a realistic projectmaster schedule on which to base the appointment of consultants, contractors, etc.
  • To give a basis controll of the project to makeit possible for the client to monitor actual progress and if necessary take corrective actions
  • To establish a realistic time period for the construction stage
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. What is a pre-contract planning? Give an example as regards a pre-contract programme! Give some important reasons for a pre-contract planning!
A

It is prepared by the contractor: ”the contracters planning considerations during the preparation of an estimate” reasons:
• To aid the tendering process in general
• To establish a realistic contract period on which the tender may be based
• To identify construction methods
• To assess method-related itemswhich affect the bid price.
• To aid the buil-up contract preliminaries and plant expenditure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What do we mean by contract planning?

A

It is the more detailed planningand it will be further developed during the construction stage. It’s made by main contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. The contract planning can be done in different levels. Mention three such levels!
A

scsad

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

8.Name five important general guide-lines as regards planning of a project!

A
  • Getting a feel for the project
  • Establishing key project dates
  • Establishing key activities or events
  • Assessing how long the activities will take
  • Esablishing the sequence
  • Deciding which programming technique to use (for time-planning, analysis, and presentation)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Name the seven steps in the “Seven steps systematics”
A
  • Clarify the task
  • Present alternatives
  • Collect data
  • Prepare programmes and detailed plans
  • Achieve necessary approvals
  • Execute the construction according to the programmes and plans
  • Follow up
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. Describe the content in step 1 of the “Seven steps systematics”
A

The aim with step 1 is to become acquainted with the project

  • study documents, drawings, specifications
  • interview the client and the clients representive
  • study the constructions site
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. Describe the content in step 3 of the “Seven steps systematics”
A

the aim with step 3 is to achieve necessary data regarding production operations, methods, resources
• Study ”the company archive”, handbooks, other relavant literature
• Make interviews
• Make study-visits
• In some cases make trial operations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. Describe the content in step 7 of the “Seven steps systematics”
A

”follow up”
Aim: to make sure that the plans/programmes are followed and to collect data for the future
• Follow up of cost-data, time-data, and quality-data
• Work measurement on activities of special intresst
• Analysis of new methods, materials, and machines
• Analysis of parts of the production where estimations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. What do we mean by “work breakdown structure”? When is it especially important?
A

Itis when you divied the project to smaller packagest hat can be estimated, planed, assigned and controlled. It is especially important in big projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a lead-time?

A

Time needed to purchas/order, design, produce and, deliver a product. Lead-times will affect the planning of a construction project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly