Chapter 8 : Project Control : introduction to earned value mgmt Flashcards
3 learning objectives, introduction to earned value
- concept of productivity
- S-curve or cumulative cost curve
- concept of earned value
what is EVM
EVM is a project control technique
what does EVM stands for
earned value mgmt
EVM measures the _______ _____ _______ ________ at any point in time during its ______
EVM measures the performance of a project at any point in time over its duration.
What does the EVM integrates to measure the project’s performance and progress?
- cost
- schedule
- scope
The ___ ____ _____ is a plot of a project’s ____ _____ _____ with the actual cost of work performed and ____ ____ ___ ___ _____
The cost schedule plan is a plot of a project’s planned cumulative costs that serve as a basis for comparison with the actual cost of work performed and budgeted cost of work performed.
what does an S-curve refers to?
the plot of a project’s planned cumulative costs
what is BCWS equal to?
PV
what is BCWP equal to?
EV
what is the meaning of BCWS
budgeted cost of work scheduled.
“authorized budget assigned to the work to be accomplished for an activity”
what is the meaning of BCWP
budgeted cost of work performed
“how much of the budget should have been spent based on the actual amount of work performed”
planned expenditures at their actual times
formula for earned value
EV = BCWP = % complete x total budgeted cost
what is ACWP equal to?
AC
what is the meaning of ACWP?
actual of work performed.
“actual cost incurred in accomplishing the work”
what is the meaning of BAC?
budget at completion
“total planned value PV of a project, total estimated cost of the project”