Chapter 7 Flashcards
1
Q
cost indexes formula
A
(cost A/cost B)=(index value time A / index values time B)
2
Q
power-sizing model formula
A
( cost equipment A / cost equipment B ) = ( capacity A / capacity B ) ^x
3
Q
what is the six-tenths rule?
A
x = 0,6
4
Q
nuclear generating plants, x =
A
x = 0,68
5
Q
fossil-fuel generating plants, x =
A
x = 0,79
6
Q
general conditions for rough estimates (6)
A
- exclude special location conditions (historical)
- sizing factor
- inflation index
- local index, construction costs
- different regulatory constraints
- local factors for new facility