Chapter 5 : Project delivery systems and work breakdown structure Flashcards
Learning objectives, project delivery systems and work breakdown structure (4)
- understand the basis of project delivery systems
- types of project delivery systems
- reasons for planning and the elements of the project master plan
- what is a work breakdown structure
3 synonyms of project delivery systems
- contracting method
- contract strategy
- procurement strategy
What is a project delivery system?
- a framework for the relationship between the owner and other project participants
______ should be delegated to the party who has the most _____ to control them
Risks should be delegated to the party who has the most ability to control them.
4 types of project delivery systems
- traditional (design-bid-build)
- turnkey (design-build and design-manage)
- owner-builder
- professional construction mgmt (general contractor and project manager)
What types of contracts are usually established during a traditional project delivery system, between the owner and the general contractor?
- lump sum, unit price or cost plus fixed fee contract
What type of project delivery system is represented? Owner enters in contact with a single designer and a single general contractor.
traditional
What type of project delivery system is represented? Owner enters in contact with an (engineer and contractor)
turnkey, design-build
What type of project delivery system is represented? Owner enters in contact with an (engineer and construction manager)
turnkey, design-manage