Chapter 7 Flashcards

1
Q

Name the two discretionary funding allocations a project may receive.

A

Contingency Reserve and Management Reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Name the negative risk responses

A

Accept, Avoid, Transfer, Mitigate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Name the positive risk responses

A

Exploit, Share, Enhance, Accept

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Choosing to accept the consequences of the risk

A

Accept

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Actual cost of completing the work component in a given time period

A

Actual Costs AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Avoiding the risk altogether or eliminating the cause of the risk event.

A

Avoid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

the most precise cost estimating technique. It assigns a cost to each work package on the project. It is also the costliest.

A

Bottom-Up Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

the process of aggregating all the cost estimates and establishing a cost baseline.

A

Budgeting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How fast you’re going through the money

A

Burn Rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Certain amount of money set aside to cover costs resulting from possible adverse events or unexpected issues on the project. PM usually controls

A

Contingency Reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

the total expected cost for the project.

A

Cost Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Measures the value of work completed at the measurement date against the actual cost.

A

Cost Performance Index CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Measures actual performance to date against what’s been spent.

A

Cost Variance CV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Performance measurement technique that compares what your project has produced to what you’ve spent by monitoring the planned value, earned value, and actual costs expended to produce the work of the project.

A

Earned Value Measurement EVM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Value of the worked completed to date as it compares to budgeted amount (PV) for that period. Example: Budgeted amount is $1k. 30 percent of work completed. This is $300

A

Earned Value EV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Monitoring the probability or impact of the risk event to assure benefits are realized.

A

Enhance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The expected cost to finish all the remaining project work

A

Estimate to Completion ETC

18
Q

Includes measuring the project spending to date, determining the burn rate, and tracking expenditures to the cost baseline so that stakeholders can see what was planned versus what actually spent on the project.

A

Expenditure Tracking

19
Q

Mechanism used to report on the current state of the project budget

A

Expenditure Reporting

20
Q

Looking for opportunities to take advantage of positive impacts.

A

Exploit

21
Q

Consequence or opportunity the risk poses to the project if it occurs. Can be defined as:

  • High: 1.0
  • Medium: 0.5
  • Low: 0.1
A

Risk Impact

22
Q

Amount set aside by upper management to cover future situations that can’t be predicted. Contingency spending authority is under the discretion of the project manager or upper management.

A

Management Reserve

23
Q

Reducing the impact or the probability of the risk.

A

Mitigate

24
Q

A cost-estimating technique that uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project; also called analogous estimates. They are the least accurate and least expensive.

A

Top Down Estimating / Order-of-Magnitude Estimating

25
Q

The cost of the work that has been authorized and budgeted for a specific schedule activity or WBS component during a given time period or phase

A

Planned Value PV

26
Q

the likelihood that a risk event will occur, expressed as a number from 0.0 to 1.0 with 1 being absolute certainty.

A

Probability

27
Q

a tool for the project team to aid in prioritizing risks.

A

Probability and Impact Matrix

28
Q

Potential future event that can have either negative or positive impacts on the project.

A

Risk

29
Q

Process of identifying those risks that have the greatest possibility of occurring and the greatest impact to the project if they do occur.

A

Risk Analysis

30
Q

The process of determining and documenting the potential risks that could occur on your project.

A

Risk Identification

31
Q

Deals with how you manage the areas of uncertainty in your project. Identify, analyze, and develop a response.

A

Risk Planning

32
Q

List of risks that you can record in a simple spreadsheet that includes an identification number, risk name, description, risk owner, and response plan.

A

Risk Register

33
Q

the process of developing options, and determining actions to enhance opportunities and reduce threats to the project’s objectives

A

Risk Response Plan

34
Q

Sign or a precursor signaling that a risk event is about to occur.

A

Risk Triggers

35
Q

Measures the progress to date against the progress that was planned.
• Formula: SPI = EV/PV
• Results: <1: Behind schedule >1: Ahead of schedule

A

Schedule Performance Index SPI

36
Q

Compares an activity’s actual progress to date to the estimated progress and is represented in terms of cost.

A

Schedule Variance

37
Q

Assigning the risk to a third party who is best able to bring about the opportunity.

A

Share

38
Q

SWOT

A

Strengths, Weaknesses, Opportunities, and Threats.

39
Q

Involves analyzing the project from each perspective: strengths, weaknesses, opportunities, and threats.

A

SWOT Analysis

40
Q

Average of the most likely estimate, the optimistic estimate, and the pessimistic estimate. Subject matter experts should give the estimates.
• Formula: Estimate + Optimistic + Pessimistic/3

A

Three-Points Estimate

41
Q

Moving the liability for the risk to a third party by purchasing insurance, performance bonds, and so on.

A

Transfer

42
Q

The total time it takes for a person to complete the task if they do nothing else from the time they start until the task is completed. Need to know actual hours spent performing task. Example resource is spending 5 hours a day over 4 days. Work effort is 20 hours.

A

Work Effort