Chapter 7 Flashcards

1
Q

Risk

A

Uncertain or chance events that planning may not be able to overcome or control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Risk Management

A

A proactive attempt to recognize and manage internal events and external threats that affect the likelihood of a project’s success.

What can go wrong (risk event).
How to minimize the risk event’s impact (consequences).
What can be done before an event occurs (anticipation).
What to do when an event occurs (contingency plans).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Benefits of Risk Management

A

A proactive rather than reactive approach.
Reduces surprises and negative consequences.
Prepares the project manager to take advantage of appropriate risks.
Provides better control over the future.
Improves chances of reaching project performance objectives within budget and on time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Managing Risk Steps

A

Step 1: Risk Identification
Step 2: Risk Assessment
Step 3: Risk Response Development
Step 4: Risk Response Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Step 1: Risk Identification

A

Generate a list of possible risks through brainstorming, problem identification and risk profiling.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Step 2: Risk Assessment

A

Scenario analysis for event probability and impact
Risk assessment matrix
Failure Mode and Effects Analysis (FMEA)
Probability analysis
Decision trees, NPV, & Program Eval. Review Technique (PERT)
Semi-quantitative scenario analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Step 3: Risk Response Development

A

Mitigating Risk
Avoiding Risk
Transferring Risk
Retaining Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Step 4: Risk Response Control

A
Risk control
Execution of the risk response strategy
Monitoring of triggering events
Initiating contingency plans
Watching for new risks

Establishing a Change Management System
Monitoring, tracking, and reporting risk
Fostering an open organization environment
Repeating risk identification/assessment exercises
Assigning and documenting responsibility for managing risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Contingency Plan

A

An alternative plan that will be used if a possible foreseen risk event actually occurs.
A plan of actions that will reduce or mitigate the negative impact (consequences) of a risk event.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Risks of Not Having a Contingency Plan

A

Having no plan may slow managerial response.

Decisions made under pressure can be potentially dangerous and costly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Technical Risks

A

Backup strategies if chosen technology fails.

Assessing whether technical uncertainties can be resolved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Schedule Risks

A

Use of slack increases the risk of a late project finish.
Imposed duration dates (absolute project finish date)
Compression of project schedules due to a shortened project duration date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Cost Risks

A

Time/cost dependency links: costs increase when problems take longer to solve than expected.
Price protection risks (a rise in input costs) increase if the duration of a project is increased.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Funding Risks

A

Changes in the supply of funds for the project can dramatically affect the likelihood of implementation or successful completion of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Risk and Contingency Planning

A

Technical Risks
Schedule Risks
Cost Risks
Funding Risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Exploit

A

Seeking to eliminate the uncertainty associated with an opportunity to ensure that it definitely happens.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Share

A

Allocating some or all of the ownership of an opportunity to another party who is best able to capture the opportunity for the benefit of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Enhance

A

Taking action to increase the probability and/or the positive impact of an opportunity.

19
Q

Accept

A

Being willing to take advantage of an opportunity if it occurs, but not taking action to pursue it.

20
Q

Opportunity Management Tactics

A

Exploit
Share
Enhance
Accept

21
Q

Contingency Funds

A

Funds to cover project risks—identified and unknown.
Size of funds reflects overall risk of a project

Budget reserves
Are linked to the identified risks of specific work packages.

Management reserves
Are large funds to be used to cover major unforeseen risks (e.g., change in project scope) of the total project.

22
Q

Time Buffers

A

Amounts of time used to compensate for unplanned delays in the project schedule.
Severe risk, merge, noncritical, and scarce resource activities

23
Q

Change Control System Process

A

Identify proposed changes.
List expected effects of proposed changes on schedule and budget.
Review, evaluate, and approve or disapprove of changes formally.
Negotiate and resolve conflicts of change, condition, and cost.
Communicate changes to parties affected.
Assign responsibility for implementing change.
Adjust master schedule and budget.
Track all changes that are to be implemented.

24
Q

Benefits of a Change Control System

A

Inconsequential changes are discouraged by the formal process.
Costs of changes are maintained in a log.
Integrity of the WBS and performance measures is maintained.
Allocation and use of budget and management reserve funds are tracked.
Responsibility for implementation is clarified.
Effect of changes is visible to all parties involved.
Implementation of change is monitored.
Scope changes will be quickly reflected in baseline and performance measures.

25
Q

PERT—Program Evaluation Review Technique

A

Assumes each activity duration has a range that statistically follows a beta distribution.
Uses three time estimates for each activity: optimistic, pessimistic, and a weighted average to represent activity durations.
Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project durations.

26
Q

_____ is a proactive approach rather than a reactive

A

Risk Management

27
Q

The sources of ______ are unlimited

A

project risk

28
Q

____ is usually excluded from the disucssion or project risk as it has already been accounted for

A

External risk

29
Q

Risk Breakdown Structure (RBs)

A

A hierarchical depiction of identified project risks arranged by risk category that identifies the various areas and causes of potential risks.

30
Q

Risk profile

A

a list of questions that address traditional areas of uncertainty on a project

31
Q

Scenario analysis

A

the easiest and most commonly used technique for analyzing risks

32
Q

Team members assess the significance of each risk event in terms of:

A

Probably of the event

Impact of each event

33
Q

Failure Mode and Effects Analysis (FMEA)

A

extends the risk severity matrix by including ease of detection inn the equation:
Impact x Probability x Detection = Risk Value

34
Q

Mitigating Risk

A

Reducing the likelihood an adverse event will occur.

Reducing impact of adverse event.

35
Q

Avoiding Risk

A

Changing the project plan to eliminate the risk or condition.

36
Q

Transferring Risk

A

Paying a premium to pass the risk to another party.

Requiring Build-Own-Operate-Transfer (BOOT) provisions.

37
Q

Retaining Risk

A

Making a conscious decision to accept the risk.

38
Q

Budget Reserves

A

Identified for specific work packages or segments of a project found in the baseline budget or work breakdown structure

39
Q

Management Reserves

A

Funds are needed to cover major unforeseen risks and, hence, are applied to the total project

40
Q

Major scope change may appear nessary midway in the project. What reserve would be used

A

Management Reserves

41
Q

Time Buffers

A

Cushion against potential delays in project.

42
Q

Change Control Process

A
  1. Change Originates
  2. Change Request Submitted
  3. Review Change Request
  4. Approve
  5. Update Plan of Record
  6. Distribute for Action
43
Q

Change Management system

A

involve reporting, controlling, and recording changes to the project baseline.

44
Q

The benefits from a change in control systems

A
  1. Inconsequential changes are discouraged by the formal process
  2. Cost of changes are maintained in a log
  3. Integrity of the WBS and performance measures is maintained
  4. Allocation and use of budget and management reserve funds are tracked
  5. Responsibility for implementation is clarified
  6. Effect of changes is visible to all parties involved
  7. Implementation of change is monitored
  8. Scope changes will be quickly reflected in baseline and performance measures