Chapter 6 Flashcards

1
Q

Developing a Project Network

A

What is a project network?
What is a critical path?
What is sequencing?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The Project Network

A

A flow chart that graphically depicts the sequence, interdependencies, start and finish times of the activities within the project job plan that is the critical path through the network.

Provides the basis for scheduling labor and equipment.
Enhances communication among project participants.
Provides an estimate of the project’s duration.
Provides a basis for budgeting cash flow.
Identifies activities that are critical.
Highlights activities that are “critical” and can not be delayed.
Helps project managers get and stay on plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Constructing a Project Network

A

Activity
Merge Activity
Parallel (Concurrent) Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Activity

A

an element of the project that requires time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Merge Activity

A

an activity that has two or more preceding activities on which it depends.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Parallel (Concurrent) Activities

A

Activities that can occur independently and, if desired, at the same time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Path

A

a sequence of connected, dependent activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Critical path

A

the longest path through the activity network that allows for the completion of all project-related activities. Delays on the critical path will delay completion of the entire project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Event

A

represents a point in time where an activity starts or ends.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Burst activity

A

has more than one activity immediately following it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Activity-on-node (AON)

A

uses a node to depict an activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Activity-on-arrow (AOA)

A

uses an arrow to depict an activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Basic Rules in Developing Project Networks

A

Networks typically flow from left to right.
An activity cannot begin until all preceding connected activities are complete.
Arrows indicate precedence and flow and can cross over each other.
Each activity must have a unique identifying number that is greater than any of its predecessor activities.
Looping is not allowed.
Conditional statements are not allowed.
Use common start and stop nodes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Network Computation Process

A

Forward Pass—Earliest Times
How soon can the activity start? (early start—ES)
How soon can the activity finish? (early finish—EF)
How soon can the project finish? (expected time—ET

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Forward Pass Computation

A

Add activity times along each path in the network (ES + Duration = EF).
Carry the early finish (EF) to the next activity where it becomes its early start (ES) unless…
The next succeeding activity is a merge activity, in which case the largest EF of all preceding activities is selected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Network Computation Process

A

Backward Pass—Latest Times
How late can the activity start? (late start—LS)
How late can the activity finish? (late finish—LF)
Which activities represent the critical path? (CP)
How long can activity be delayed? (slack or float—SL)
How long an activity can be delayed without effecting the successor activity = FS (free slack)

17
Q

Backward Pass Computation

A

Subtract activity times along each path in the network (LF - Duration = LS).
Carry the late start (LS) to the next activity where it becomes its late finish (LF) unless …
The next succeeding activity is a burst activity, in which case the smallest LF of all preceding activities is selected.

18
Q

Use of Lags

A

Lags
The minimum amount of time a dependent activity must be delayed to begin or end.
Lengthy activities are broken down to reduce the delay in the start of successor activities.
Lags can be used to constrain finish-to-start, start-to-start, finish-to-finish, start-to-finish, or combination relationships.

19
Q

Use of Lags - Relationships

A

Finish-to-start relationship – one activity must be complete before the next activity can be started

Start-to-start relationship, activities can start before the predecessor is completed

20
Q

Hammock Activity

A

Spans over a segment of a project.
Has a duration that is determined after the network plan is drawn.
Is used to aggregate sections of the project to facilitate getting the right amount of detail for specific sections of a project.
Is very useful in assigning and controlling indirect project costs.

21
Q

WBS & Project Networking

A

How is project networking different from WBS?
How are the WBS & Project Networking linked?
Why have a WBS? Why not have just a Project Network?