Chapter 5 Flashcards

1
Q

Estimating

A

The process of forecasting or approximating the time and cost of completing project deliverables.
The task of balancing expectations of stakeholders and need for control while the project is implemented.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Estimating Projects

A

To support good decisions.
To schedule work.
To determine how long the project should take and its cost.
To determine whether the project is worth doing.
To develop cash flow needs.
To determine how well the project is progressing.
To develop time-phased budgets and establish the project baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Estimating Guidelines for Time, Costs, Resources

A

Have people familiar with the tasks make the estimate.
Use several people to make estimates.
Base estimates on normal conditions, efficient methods, and a normal level of resources.
Use consistent time units in estimating task times.
Treat each task as independent, don’t aggregate.
Don’t make allowances for contingencies.
Adding a risk assessment helps avoid surprises to stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Top-Down Estimates (macro)

A

Are usually are derived from someone who uses experience and/or information to determine the project duration and total cost.
Are made by top managers who have little knowledge of the processes used to complete the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Bottom-Up Approach (micro)

A

Can serve as a check on cost elements in the WBS by rolling up the work packages and associated cost accounts to major deliverables at the work package level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Estimating Projects: Preferred Approach

A
Make rough top-down estimates.
Develop the WBS/OBS.
Make bottom-up estimates.
Develop schedules and budgets.
Reconcile differences between top-down and bottom-up estimates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Level of Detail

A
Level of detail is different for different levels of project management.
Level of detail in the WBS varies with complexity of the project.
Excessive detail is costly.
Fosters a focus on departmental outcomes
Creates unproductive paperwork
Insufficient detail is costly.
Lack of focus on goals
Wasted effort on nonessential activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Types of Costs

A

Direct Costs
Direct (Project) Overhead Costs
General and Administrative Overhead Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Direct Costs

A

Costs that are clearly chargeable to a specific work package.
Labor, materials, equipment, and other

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Direct (Project) Overhead Costs

A

Costs incurred that are directly tied to an identifiable project deliverable or work package.
Salary, rents, supplies, specialized machinery

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

General and Administrative Overhead Costs

A

Organization costs indirectly linked to a specific package that are apportioned to the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Refining Estimates

A
Reasons for Adjusting Estimates
Interaction costs are hidden in estimates.
Normal conditions do not apply.
Things go wrong on projects.
Changes in project scope and plans.

Adjusting Estimates
Time and cost estimates of specific activities are adjusted as the risks, resources, and situation particulars become more clearly defined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly