Chapter 5 Basic Fitting for Steam Boilers Flashcards

1
Q
  1. The types of construction used with packaged boilers are:
  2. “A”
  3. “B”
  4. “C”
  5. “D”
  6. “O”
A. 1, 2, 3 
B. 2, 3, 5 
C. 3, 4, 5 
D. 1, 3, 5 
E. 1, 4, 5
A

E. 1, 4, 5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
2. Water circulation in the longitudinal drum boiler is created by: 
A. The water circulation pump. 
B. Higher density feedwater 
C. Higher density boiler water 
D. Lower density boiler water 
E. Direction of feedwater supply
A

B. Higher “density feedwater”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. The boilers or modules in a multiple heating boiler plant are:

A. Most typically connected in series between the supply and return header

B. Most typically connected in parallel after the supply header

C. Most typically connected in parallel between the supply and return header

D. Most typically connected in parallel before the return header

E. Fired by a common burner control system

A

C. Most typically connected in “parallel between” the supply and return header

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. An advantage of a multiple heating boiler plant is:

A. That they have a large water capacity

B. The boilers are heavy requiring special foundations

C. That with a small water content a pressure part failure will cause more damage

D. They are light requiring a minimal foundation

E. Most low capacity can be moved through standard sized doorways

A

E. Most low capacity can be moved through standard sized doorways

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

5.The boilers in multiple boiler heating plants are operated:

A. In sequence by a step controller

B. Individually by separate controllers

C. By the outdoor temperature

D. By temperature controller

E. Manually as required

A

A. In sequence by a step controller

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. Blowdown valves are installed to:
  2. Remove any accumulation of sediment
  3. Remove contaminated steam
  4. Drain the boiler
  5. Lower the concentration of dissolved impurities in the steam
  6. Lower the concentration of dissolved impurities in the water
A. 1, 2, 3 
B. 2, 3, 5 
C. 3, 4, 5 
D. 1, 3, 5 
E. 2, 4, 5
A

D. 1, 3, 5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. A safety valve must be mounted:
  2. In the horizontal position
  3. To the boiler by a short nipple
  4. At the highest practicable part of the boiler
  5. With discharge water properly drained
  6. With a valve next to the boiler
A. 1, 2, 3 
B. 2, 3, 4 
C. 3, 4, 5 
D. 1, 3, 5 
E. 2, 4, 5
A

B. 2, 3, 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. A pressure gauge can most accurately be calibrated by using:
A. The Inspector’s test gauge 
B. A dead weight tester 
C. A test gauge comparator 
D. Hydraulic comparator 
E. Another pressure gauge
A

B. A dead weight tester

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. A check valve is used in the feedwater line to prevent:

A. Water hammer in the feedwater line
B. A reverse flow of steam from the boiler
C. A reverse flow of water from the boiler
D. Air from entering the feedwater line
E. A reverse of water from the feedwater lin

A

C. A reverse flow of water from the boiler

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. Quick closing gauge glass valves are operated by:
A. Valve rods 
B. Actuators 
C. Solenoids 
D. Diaphragms 
E. Levers and chains
A

E. Levers and chains

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. Before feedwater enters a boiler the feedwater pipe must be fitted with a:

A. Gate valve between the check valve and the boiler
B. Stop valve between the check valve and the boiler
C. Globe valve between the check valve and the boiler
D. Ball valve between the check valve and the boiler
E. Check valve between the stop valve and the boiler

A

B. Stop valve between the check valve and the boiler

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. The “popping” pressure of a safety valve may be increased by:
A. Rising the adjusting ring 
B. Lowering the adjusting ring 
C. Increasing the spring pressure
D. Decreasing the spring pressure 
E. Raising the lifting lever
A

C. Increasing the spring pressure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. A Bourdon tube is in the shape of:
A. An oval in the cross section 
B. The letter “C” 
C. A bellows 
D. The letter “C” and oval in cross section 
E. A diaphragm
A

D. The letter “C” and oval in cross section

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

14.When the pressure in the boiler approaches its _____, the safety valve will pop open and release the steam to atmosphere.

A. Normal steam drum operating pressure 
B. Maximum allowable working pressure 
C. Normal process header steam pressure 
D. Turbine inlet operating pressure 
E. Ultimate tensile strength
A

B. Maximum allowable working pressure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. Try cocks are used on boilers to:
A. Test for steam pressure 
B. Prove the temperature of the steam 
C. Test the operation of the safety valve 
D. Drain water from the water column 
E. Check the boiler water level
A

E. Check the boiler water level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. Boiler gauge glass packing nuts may be tightened:
A. At any time 
B. Once the pressure has been removed 
C. Once the glass has cooled to room temperature 
D. With a torque wrench 
E. Only hand tight
A

B. Once the pressure has been removed

17
Q
  1. Boiler fittings must comply with the requirements set out in the:
  2. ASME Codes
  3. ANSI Codes
  4. CSA B51
  5. CSA B52
  6. The regulations of the authority having jurisdiction
    A. 1, 2, 3
    B. 2, 3, 4
    C. 3, 4, 5
    D. 1, 3, 5
    E. 2, 3, 5
A

D. 1, 3, 5

18
Q
  1. All fittings not properly or clearly identified:
    A. May be used for low pressure service
    B. Can be used in water applications
    C. Can be used for compressed air service
    D. Should be kept for emergency use
    E. Should be rejected
A

E. Should be rejected

19
Q
19. The boiler "vent valve" is used for the purpose of allowing:
A.	Steam to escape while filling
B.	Air to escape while draining
C.	Water to escape while filling
D.	Steam to enter while draining
E.	Air to escape while filling
A

E. Air to escape while filling

20
Q
20. Gauge glass safety shutoff valves are equipped with a:
A.	Floating disc
B.	Flapper disc
C.	Stainless steel ball
D.	Brass plug
E.	Self closing stem
A

B. Flapper disc

21
Q
Answer Chapter 5
 Basic Fitting for Steam Boilers
1.	E
2.	B
3.	C
4.	E
5.	A
6.	D
7.	B
8.	B
9.	C
10.	E
11.	B
12.	C
13.	D
14.	B
15.	E
16.	B
17.	D
18.	E
19.	E
20.	C
A