Q
- In the circulating method, the acid solution is circulated continuously through the unit at a temperature of about _____ until the cleaning action is completed as shown by tests.
A. 100°C (212°F) B. 65°C (150°F) C. 50°C (98°F) D. 120°C (248°F) E. 77°C (170°F)
A
B. 65°C (150°F)
2
Q
- The boiler inhibited acid cleaning method most commonly uses a 5% solution of inhibited _____ acid.
A. Hydrochloric B. Sulphuric C. Nitric D. Carbonic E. Acetic
A
A. Hydrochloric
3
Q
- When the boiler water has cooled to about _____ open the blowdown valves and drain the boiler.
A. 90°C (194°F) B. 110°C (230°F) C. 99°C (210°F) D. 134°C (273°F) E. 60°C (140°F
A
A. 90°C (194°F)
4
Q
- If damp conditions exist during the idle season, the metal surfaces should be painted with a protective coating such as:
A. Latex paint B. Oil based paint C. Light oil D. Grease E. Fuel oil
A
C. Light oil
5
Q
- In the wet boiler lay up method after the boiler water has cooled it is filled:
A. To half a gauge glass B. Completely C. To the top of the gauge glass D. To the bottom of the gauge glass E. To half fill the boiler
A
B. Completely
6
Q
- When inspecting the fireside of the boiler the surfaces are examined for bulges or blisters which would indicate:
A. Corrosion B. Erosion C. Caustic embrittlement D. Oxygen pitting E. Overheating
A
E. Overheating
7
Q
- During inhibited acid cleaning the boiler must be adequately vented because _____ is produced by the reaction of acid with iron and could cause a fire or explosion.
A. Carbon monoxide B. Carbon dioxide C. Hydrogen D. Nitrogen E. Oxygen
A
C. Hydrogen
8
Q
- When examining the waterside surfaces, the inspector will be looking for signs of:
A. Erosion B. Bulges C. Blisters D. Cracking of the metal E. Overheating
A
D. Cracking of the metal
9
Q
- Flame retarders can be found in the boiler:
A. Steam drum B. Shell C. Water tubes D. Fire tubes E. Mud drum
A
D. Fire tubes
Note:Flame retarders
10
Q
- Portable lamps of _____ or less, with current supplied from transformers or batteries, should be provided to eliminate the danger of electrocution to personnel inside the boiler.
A. 1.5 V B. 12 V C. 24 V D. 32 V E. 110 V
A
C. 24 V
11
Q
- Repairs affecting the pressure parts of a boiler may only be made after consultation with and the approval of:
A. The shift engineer B. The chief engineer C. The authorized inspector D. A qualified welder E. A professional engineer
A
C. The authorized inspector
12
Q
- Whenever there are signs of a tube leak during boiler operation:
A. Watch that it does not get worse B. Maintain a steady firing rate C. Shut down the boiler immediately D. Close the stop valve on the steam outlet E. Reduce the firing rate to the minimum
A
C. Shut down the boiler immediately
13
Q
- The internal inspection is a thorough examination of both the _____ and the _____ of the boiler.
- Fireside
- Outside
- Waterside
- Topside
A. 1, 2 B. 2, 4 C. 2, 3 D. 1, 3 E. 1, 4
A
D. 1, 3
Note: Fireside and Waterside
14
Q
- When the fires are out, allow the boiler to cool until the pressure is about _____ and then open the drum vents.
A. 35-70 kPa (5-10 psi) B. 7-35 kPa (1-5 psi) C. 70-100 kPa (10-15 psi) D. 15-20 kPa (2-3 psi) E. 20-35 kPa (3-5 psi)
A
A. 35-70 kPa (5-10 psi)
15
Q
- Chemicals used for the alkaline boil out of a boiler consist of a combination of which of the following.
- Sodium hydroxide
- Sodium sulphite
- Sodium phosphate
- Sodium carbonate
- Sodium chloride
A. 1, 2, 3 B. 2, 3, 4 C. 1, 3, 4 D. 2, 3, 4 E. 1, 2, 4
A
C. 1, 3, 4
Sodium hydroxide
Sodium phospate
Sodium carbonate