Chapter 5 Flashcards
1
Q
All of the following tasks are performed during elicitation except: Selecione uma opção de resposta: a. Select elicitation techniques b. Confirm elicitation results c. Prepare for elicitation d. Conduct elicitation activity
A
A. Select elicitation techniques
2
Q
You are reviewing documents for the current system in order to confirm the existing requirements. Document analysis is an effective technique for doing this work as long as the documents being reviewed are Selecione uma opção de resposta: a. Not current and invalid b. Not current, but valid c. Current, but not valid d. Both current and valid
A
D. Both current and valid
3
Q
What is the proper sequence for conducting a brainstorming session? Selecione uma opção de resposta: a. Reduce, reuse, and recycle b. Prepare, conduct, and wrap up c. Prepare, analyze, and reduce d. Generate, reduce, and assess
A
B. Prepare, conduct, and wrap up
4
Q
During an active observation session, the business analyst watches the user carefully, asks them probing questions, and: Selecione uma opção de resposta: a. Acts as an apprentice b. Reviews the findings c. Takes detailed notes d. Studies the process
A
C. Takes detailed notes
5
Q
What prototype allows you to learn about user interface needs and then to evolve the requirements into a fully functioning system? Selecione uma opção de resposta: a. Throw-away b. Horizontal c. Evolutionary d. Vertical
A
C. Evolutionary
6
Q
Who may participate in requirements elicitation activities? Selecione uma opção de resposta: a. Any stakeholder b. Stakeholder list c. Subject matter experts d. Project team
A
A. Any stakeholder
7
Q
“Does the existing functionality currently meet your needs?” is an example of what type of structured interview question? Selecione uma opção de resposta: a. Closed-ended b. Open-ended c. Research d. Meta question
A
A. Closed-ended
8
Q
The recommended time that your recipients must spend responding to a requirements elicitation survey is Selecione uma opção de resposta: a. Less than 5 minutes to complete b. Less than 10 minutes to complete c. Less than 15 minutes to complete d. Less than 20 minutes to complete
A
B. Less than 10 minutes to complete
9
Q
What elicitation technique might best assist you in understanding the existing processes that are being used in an online order entry system? Selecione uma opção de resposta: a. Interviewing b. Observation c. Focus group d. Prototyping
A
B. Observation
10
Q
When preparing for observation, you plan to ask questions while the work is being done. You are preparing to do \_\_\_\_\_\_\_\_\_ observation. Selecione uma opção de resposta: a. Visible b. Passive c. Invisible d. Proactive
A
A. Visible
11
Q
The Elicitation knowledge area focuses on eliciting business, stakeholder, solution, and \_\_\_\_\_\_\_\_\_\_\_\_\_ requirements. Selecione uma opção de resposta: a. Implementation b. Functional c. Transition d. Nonfunctional
A
C. Transition
12
Q
You are working with a group trying to build a list of possible approaches as to how the team might solve a specific business problem. What technique should the group consider applying? Selecione uma opção de resposta: a. Observation b. JAD session c. Focus group d. Brainstorming
A
D. Brainstorming
13
Q
You have just discovered that the business process expert for the existing system currently being upgraded is no longer employed by the company. Which elicitation technique might you apply in this situation? Selecione uma opção de resposta: a. Document analysis b. Reverse engineering c. Interface analysis d. Elicitation workshop
A
A. Document analysis
14
Q
You are planning a focus group to elicit requirements for a new online order-entry system, addressing a wide variety of end users interacting with the system in different ways. What type of users should you include in your focus group? Selecione uma opção de resposta: a. Miscellaneous b. Heterogeneous c. Homogeneous d. Collaborative
A
B. Heterogeneous
15
Q
What are the three types of interfaces typically looked at during interface analysis? Selecione uma opção de resposta: a. People, process, and project b. User, application, and device c. Input, output, and process d. User, system, and software
A
B. User, application, and device