Chapter 2 Flashcards
You are a business analyst addressing who will receive weekly business analysis status reports for your current project. You are performing tasks from which knowledge area?
Selecione uma ou mais opções de resposta:
a. Requirements Analysis
b. Business Analysis Planning and Monitoring
c. Requirements Management and Communication
d. Solution Assessment and Validation
b. Business Analysis Planning and Monitoring
You are a business analyst working on a project where the timing of the business analysis work is early in the project life cycle. What type of business analysis approach best fits this project?
Selecione uma ou mais opções de resposta:
a. Plan-driven
b. Task-driven
c. Change-driven
d. Phase-driven
a. Plan-driven
What technique might be used when determining the business analysis approach on a project?
Selecione uma ou mais opções de resposta:
a. Decision analysis
b. Expert judgment
c. Stakeholder map
d. Scope modeling
a. Decision analysis
Who is responsible for ensuring that the business analysis plan is compatible with the project plan?
Selecione uma ou mais opções de resposta:
a. Business analyst
b. Project manager
c. Implementation SME
d. Project sponsor
b. Project manager
What key input is used to plan the business analysis approach for a project?
Selecione uma ou mais opções de resposta:
a. Business need
b. Business case
c. Business goals
d. Strategic plan
a. Business need
A RACI matrix describes the roles of stakeholders involved in business analysis activities. RACI stands for:
Selecione uma ou mais opções de resposta:
a. Responsible, Accessible, Contacted, Informed
b. Responsible, Accountable, Consulted, Involved
c. Responsible, Accountable, Consulted, Informed
d. Responsible, Accountable, Coordinated, Involved
c. Responsible, Accountable, Consulted, Informed
What technique is recommended for analyzing discrepancies between planned and actual business analysis performance?
Selecione uma ou mais opções de resposta:
a. Root cause analysis
b. Business analysis
c. Variance analysis
d. Earned value analysis
c. Variance analysis
Which statement about conducting stakeholder analysis for the business analysis activities on a project is FALSE?
Selecione uma ou mais opções de resposta:
a. Done as long as business analysis work continues
b. Conducted during the project phase to which it applies
c. Performed as soon as the business need is identified
d. Determines stakeholder influence and levels of authority
b. Conducted during the project phase to which it applies
All of the following tasks are performed when planning and monitoring business analysis activities except:
Selecione uma ou mais opções de resposta:
a. Plan business analysis activities.
b. Conduct stakeholder analysis.
c. Plan business analysis approach
d. Determine solution approach.
d. Determine solution approach
Which business analysis stakeholder role is involved with all business analysis activities on a project?
Selecione uma ou mais opções de resposta:
a. Domain SME
b. Implementation SME
c. Business analyst
d. Project manager
c. Business analyst
When planning for business analysis activities, what two planning tools are commonly used?
Selecione uma ou mais opções de resposta:
a. Milestones and activities
b. Schedule and activity list
c. Resources and estimates
d. Activity list and a WBS
d. Activity list and a WBS
The business analyst has defined how, when, and why the business analysis team will work directly with project stakeholders to develop requirements. What deliverable contains this information?
Selecione uma ou mais opções de resposta:
a. Requirements management plan
b. Business analysis communication plan
c. Requirements development plan
d. Business analysis approach
b. Business analysis communication plan
What type of models can be used to define and document the business analysis approach?
Selecione uma ou mais opções de resposta:
a. Data
b. Process
c. Usage
d. Object
b. Process
What measures will the business analyst define for the business analysis activities and deliverables on a project?
Selecione uma ou mais opções de resposta:
a. Variables
b. Metrics
c. Measures
d. Forecasts
b. Metrics
What business analysis artifact is an implied input to tasks in all other knowledge areas after Business Analysis Planning and Monitoring activities are completed?
Selecione uma ou mais opções de resposta:
a. Business analysis approach
b. Business goals and objectives
c. Business analysis plan
d. Business analysis process assets
c. Business analysis plan