Chapter 4 Flashcards

1
Q

During project staffing, the primary role of senior managment is in the selection of the:
A: Project Manager
B: Assistant Project Managers
C: Functional team
D: Executives do not get involved in staffing

A

Project Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

During project staffing, the primary role of line management is:
A. Approving the selection of the project manager
B. Approving the selection of assistant project managers
C. Assigning functional resources based upon who is available
D. Assigning functional resources based upon availability and the skill set needed

A

Assigning the Functional Resources based upon availability and the skill set needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A project manager is far more likely to succeed if it is obvious to everyone that:
A. The project manager has a command of technology.
B. The project manager is a higher pay grade than everyone else on the team.
C. The project manager is over 45 years of age.
D. Executive management has officially appointed the project manager

A

Executive management has officially appointed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Most people believe that the best way to train someone in project management is through:
A. On-the-job training
B. University seminars
C. Graduate degrees in project management
D. Professional seminars and meeting

A

on the job training

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

In staffing negotiations with the line manager, you identify a work package that requires a
skill set of a grade 7 worker. The line manager informs you that he will assign a grade 6 and
a grade 8 worker. You should:
A. Refuse to accept the grade 6 because you are not responsible for training
B. Ask for two different people
C. Ask the sponsor to interfere
D. Be happy! You have two workers

A

Be Happy! You have two workers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

You priced out a project at 1000 hours assuming a grade 7 employee would be assigned. The
line manager assigns a grade 9 employee. This will result in a significant cost overrun.
The project manager should:
A. Reschedule the start date of the project based upon the availability of a grade 7
B. Ask the sponsor for a higher priority for your project
C. Reduce the scope of the project
D. See if the grade 9 can do the job in less time

A

see if the grade 9 can do the job in less time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

As a project begins to wind down, the project manager should:
A. Release all nonessential personnel so that they can be assigned to other projects
B. Wait until the project is officially completed before releasing anyone
C. Wait until the line manager officially requests that the people be released
D. Talk to other project managers to see who wants your people

A

release all non essential personnel so that they can be assigned to other projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly