Chapter 12 Flashcards

1
Q
The shortest time necessary to complete all of the activities in a network is called the:
A. Activity duration length
B. Critical path
C. Maximum slack path
D. Compression path
A

Critical Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
Which of the following  cannot be identified after performing a forward and backward
pass?
A. Dummy activities
B. Slack time
C. Critical path activities
D. How much overtime is planned
A

how much overtime is planned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
Which of the following is not a commonly used technique for schedule compression?
A. Resource reduction
B. Reducing scope
C. Fast-tracking activities
D. Use of overtime
A

resource reduction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A network-based schedule has four paths, namely 7, 8, 9, and 10 weeks. If the 10-week
path is compressed to 8 weeks, then:
A. We now have two critical paths.
B. The 9-week path is now the critical path.
C. Only the 7-week path has slack.
D. Not enough information is provided to make a determination

A

not enough information is provided to make a determination

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The major disadvantage of using bar charts to manage a project is that bar charts:
A. Do not show dependencies between activities
B. Are ineffective for projects under one year in length
C. Are ineffective for projects under $1 million in size
D. Do not identify start and end dates of a schedule

A

do not show discrepancies between activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
The first step in the development of a schedule is a:
A. Listing of the activities
B. Determination of dependencies
C. Calculation of effort
D. Calculation of durations
A

listing of activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
Reducing the peaks and valleys in manpower assignments in order to obtain a relatively
smooth manpower curve is called:
A. Manpower allocation
B. Manpower leveling
C. Resource allocation
D. Resource commitment planning
A

manpower leveling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
Activities with no time duration are called:
A. Reserve activities
B. Dummy activities
C. Zero slack activities
D. Supervision activities
A

Dummy activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
Optimistic, pessimistic, and most likely activity times are associated with:
A. PERT
B. GERT
C. PDM
D. ADM
A

PERT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
The most common “constraint” or relationship in a precedence network is:
A. Start-to-start
B. Start-to-finish
C. Finish-to-start
D. Finish-to-finish
A

finish-to-start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
A network-based technique that allows for branching and looping is:
A. PERT
B. GERT
C. PDM
D. ADM
A

GERT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If an activity on the critical path takes longer than anticipated, then:
A. Activities not on the critical path have additional slack.
B. Activities not on the critical path have less slack.
C. Additional critical path activities will appear.
D. None of the above.

A

Activities not on the critical path have additional slack

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
Which of the following is not one of the three types of dependencies?
A. Mandatory
B. Discretionary
C. Internal
D. External
A

Internal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

You have an activity where the early start is week 6, the early finish is week 10, the latest
start is week 14, and the latest finish is week 18. The slack in this activity is:
A. 4 weeks
B. 6 weeks
C. 8 weeks
D. 18 weeks

A

8 weeks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly