Chapter 12 Flashcards
The shortest time necessary to complete all of the activities in a network is called the: A. Activity duration length B. Critical path C. Maximum slack path D. Compression path
Critical Path
Which of the following cannot be identified after performing a forward and backward pass? A. Dummy activities B. Slack time C. Critical path activities D. How much overtime is planned
how much overtime is planned
Which of the following is not a commonly used technique for schedule compression? A. Resource reduction B. Reducing scope C. Fast-tracking activities D. Use of overtime
resource reduction
A network-based schedule has four paths, namely 7, 8, 9, and 10 weeks. If the 10-week
path is compressed to 8 weeks, then:
A. We now have two critical paths.
B. The 9-week path is now the critical path.
C. Only the 7-week path has slack.
D. Not enough information is provided to make a determination
not enough information is provided to make a determination
The major disadvantage of using bar charts to manage a project is that bar charts:
A. Do not show dependencies between activities
B. Are ineffective for projects under one year in length
C. Are ineffective for projects under $1 million in size
D. Do not identify start and end dates of a schedule
do not show discrepancies between activities
The first step in the development of a schedule is a: A. Listing of the activities B. Determination of dependencies C. Calculation of effort D. Calculation of durations
listing of activities
Reducing the peaks and valleys in manpower assignments in order to obtain a relatively smooth manpower curve is called: A. Manpower allocation B. Manpower leveling C. Resource allocation D. Resource commitment planning
manpower leveling
Activities with no time duration are called: A. Reserve activities B. Dummy activities C. Zero slack activities D. Supervision activities
Dummy activities
Optimistic, pessimistic, and most likely activity times are associated with: A. PERT B. GERT C. PDM D. ADM
PERT
The most common “constraint” or relationship in a precedence network is: A. Start-to-start B. Start-to-finish C. Finish-to-start D. Finish-to-finish
finish-to-start
A network-based technique that allows for branching and looping is: A. PERT B. GERT C. PDM D. ADM
GERT
If an activity on the critical path takes longer than anticipated, then:
A. Activities not on the critical path have additional slack.
B. Activities not on the critical path have less slack.
C. Additional critical path activities will appear.
D. None of the above.
Activities not on the critical path have additional slack
Which of the following is not one of the three types of dependencies? A. Mandatory B. Discretionary C. Internal D. External
Internal
You have an activity where the early start is week 6, the early finish is week 10, the latest
start is week 14, and the latest finish is week 18. The slack in this activity is:
A. 4 weeks
B. 6 weeks
C. 8 weeks
D. 18 weeks
8 weeks