Chapter 11 Flashcards

1
Q
The document that officially sanctions the project is the:
A. Project charter
B. Project plan
C. Feasibility study
D. Cost-benefit analysis
A

Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
The work breakdown structure “control points” for the management of a project are the:
A. Milestones
B. Work packages
C. Activities
D. Constraints
A

work packages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
One of the most common reasons why projects undergo scope changes is:
A. Poor work breakdown structure
B. Poorly defined statement of work
C. Lack of resources
D. Lack of funding
A

poorly defined statement of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
Which of the following generally cannot be validated using a work breakdown structure?
A. Schedule control
B. Cost control
C. Quality control
D. Risk management
A

Quality Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
The work packages in the WBS are at WBS level(s):
A. 2 only
B. 3 only
C. 4 only
D. 3 and 4
A

3 and 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
One of the outputs of the PMBOK
®
Scope Planning Process is:
A. A project charter
B. A scope statement and management plan
C. A detailed WBS
D. None of the above
A

A scope statement and management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which of the following is (are) the benefit(s) of developing a WBS to low levels?
A. Better estimation of costs
B. Better control
C. Less likely that something will “fall through the cracks”
D. All of the above

A

all of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The PMBOK
®
Scope Verification Process is used to verify that:
A. The budget is correct.
B. The scope is correct.
C. The schedule is correct.
D. A life-cycle phase or the end of the project has been completed successfully

A

the scope is correct

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Financial closeout, which is often part of following the Scope Verification Process, is used to:
A. Close out all charge numbers
B. Close out all charge numbers for the work performed and completed
C. Amend the work authorization forms
D. None of the above

A

close out all charge numbers for the work performed and completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

One of your contractors has sent you an e-mail requesting that they be allowed to conduct
only eight tests rather than the ten tests required by the specification. What should the project manager do first?
A. Change the scope baseline
B. Ask the contractor to put forth a change request
C. Look at the penalty clauses in the contract
D. Ask your sponsor for his or her opinion

A

ask the contractor to put forth a change request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

One of your contractors sends you an e-mail request to use high quality raw materials in
your project stating that this will be value-added and improve quality. What should the project manager do first?
A. Change the scope baseline
B. Ask the contractor to put forth a change request
C. Ask your sponsor for his or her opinion
D. Change the WBS

A

ask the contractor to put forth a change request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
What are the maximum number of subsidiary plans a program management plan can contain?
A. 10
B. 15
C. 20
D. Unlimited number
A

unlimited number

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The change control board, of which you are a member, approves a significant scope
change. The first document that the project manager should updated would be the:
A. Scope baseline
B. Schedule
C. WBS
D. Budget

A

scope baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly