Chapter 3 Flashcards

1
Q
In which organizational form is it most difficult to integrate project activities?
A. Classical/traditional
B. Projectized
C. Strong matrix
D. Weak matrix
A

Classical/Traditional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
In which organization form would the project manager possess the greatest amount of 
authority?
A. Classical/traditional
B. Projectized
C. Strong matrix
D. Weak matrix
A

Projectized

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
In which organizational form does the project manager often have the least amount of 
authority?
A. Classical/traditional
B. Projectized
C. Strong matrix
D. Weak matrix
A

Strong Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
In which organizational form is the project manager least likely to share resources with other
projects?
A. Classical/traditional
B. Projectized
C. Strong matrix
D. Weak matrix
A

Projectized

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
In which organizational form do project managers have the greatest likelihood of possessing reward power and have a wage-and-salary administration function? (The project and line
manager are the same person.)
A. Classical/traditional
B. Projectized
C. Strong matrix
D. Weak matrix
A

Classical/Traditional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
In which organizational form is the worker in the greatest jeopardy of losing his or her job
if the project gets canceled?
A. Classical/traditional
B. Projectized
C. Strong matrix
D. Weak matrix
A

projectized

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
In which type of matrix structure would a project manager most likely have a command of
technology?
A. Strong matrix
B. Balanced matrix
C. Weak matrix
D. Cross-cultural matrix
A

Strong matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly