Chapter 21 Project Admin & Execution Flashcards
OBS
Organization breakdown structure - an org chart for a project used to show who is responsible for certain teams. Shows all parties needed to complete the SoW
WBS
work breakdown structure
WBS must include
Planning and design activities
project approval and start
implementation of work elements
completing/closing out project
PERT
network diagram chart to identify predecessor and successor relationships on projects
CPM uses a similar network diagram by identifying the chain of events that take the longest time to complete. End date of project is identified and determined by critical path
Both CPM & PERT use timelines to integrate logical activities and identify critical paths
PERT diagrams are used to calculate start and end date of each activity on the project
Gantt Chart
shows duration of activity using bar chart
doesnt identify successor/predecessors
PERT formula
(Optimistic + (4*most likely)+pessimistic)/6
Codes purposes
ensure a minimal level of acceptable performance and address safety of persons and property in the installation or use of a system (not functionality)
Closeout Plan roles
ICT designer develops a custom closeout plan for each project. Designer manages and approves plan. PM and contractors execute the plan.
Closeout Plan duties
-Compile required documentation
-Deliver/transmit all closeout docs
-Track/document closeout doc submittals, including:
–Extra materials
–spare parts
–warranties
–O&M docs
–record drawings
–training records
–test results
-Review/reference project docs
-Communicate document anomalies to responsible parties (punch list)
-accept reviewed docs and stamp as approved
-Deliver any required training
Design Development ICT tasks
-Peer review as an independent party
-Evaluate the ICT design doc for standards, code compliance, and/or specific client requests
-Identifying potential value engineering opportunities
-Identifying any conflicts that may become apparent
If submittal is rejected or has comments, ICT designer may need to:
-Review Contract requirements and revise submittal for compliance
-Submit alternative product to meet contract requirements
-Request a variance for the contract requirements
Contractor submittal items include:
COI
Surety Bonds
BoM
Lists of subs and products
Schedules of activities
Shop drawings
Product data
Samples
test reports
Technical and user manuals
Project Photos
Three Elements of Design
Specifications
Drawings
Cost Estimates
Four types of specifications
Performance - result focus, contractor selects equipment to deliever result
Proprietary - products are hard spec
Descriptive - focus is on exact properties and install methods
Reference - requirements are based on an established standard
Party responsible for producing specifications for a project
ICT design professional