Chapter 14 - Risk Assessment in Investment Appraisal Techniques Flashcards

1
Q

Risk assessment methods

A
  • Non-probabilistic
    – sensitivity analysis
    – scenario analysis
    – simulation modelling
  • Probabilistic approaches
    – expected net present value (ENPV) and standard deviation
    – event tree diagrams
  • Risk-adjusted discount rate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Risk-seeing / risk-neutral / risk-adverse investors

A
  • Risk-seeking: these are investors who accept greater volatility and uncertainty in investments or trading in exchange for anticipated higher returns. Risk-seeking investors are more interested in capital gains from speculative assets than investments with lower risks with lower returns. For example, a risk seeker would prefer investing their money in stocks as they have the potential to give higher returns than fixed deposits.
  • Risk-averse : these are investors who avoid risks and prefer lower returns with known risks rather than
    higher returns with unknown risks. Most investors and managers are risk-averse and require an additional return to compensate for any additional risk. For example, a risk-averse person would prefer investing in fixed deposits, government bonds and so on that involve less risk and provide a more certain return compared to stocks.
  • Risk-neutral : these investors overlook risk when deciding between investments. They are only
    concerned with an investment’s estimated return.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is sensitivity analysis?

A

Sensitivity analysis is a non-probabilistic approach used in investment appraisal that allows the analysis of changes in assumptions made in the forecast. It is a tool for quantitative risk assessment that predicts the outcome of a decision by ascertaining the most critical variables and their effect on the decision. It examines how sensitive the returns on a project are to changes made to each of the key variables, such as any increase or decrease in
* capital costs
* projected sales volumes
* variable costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Sensitivity analysis methodology

A

The methodology follows the steps below.
1. Specify a base case situation and calculate the NPV of the project based on the best estimates and assumptions. Only projects that generate a positive NPV are accepted.
2. Calculate the percentage change (or sensitivity) of each of the variables that would result in the breakeven position (with a NPV of zero). Any further change resulting in negative NPV would change the decision. For example, what impact would the projected sales have on NPV if they decreased or increased by 10%? What if demand fell by 10% compared to the original forecasts? Would the project still be viable? How much of a fall in demand can be accepted before the NPV falls below zero or below the breakeven?

Sensitivity margin = (NPV ÷ PV of flow under consideration) × 100%

The lower the sensitivity margin, the more sensitive the decision to the particular variable under consideration. A small change in the estimate could change the NPV from positive (accept) to negative (reject).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Advantages and Disadvantages of sensitivity analysis

A

Advantages
* The analysis is based on a simple theory, can be calculated on a spreadsheet and is easily understood.
* It identifies areas and estimates crucial to the success of the project. These critical areas are carefully monitored if the project is chosen.
* It provides information to allow management to make subjective judgements based on the likelihood of the various possible outcomes.
* The analysis is used by a range of organisations. For example, this technique is popular in the National Health
Service (NHS) for capital appraisal.

Disadvantages
* The technique changes one variable at a time which is unlikely to happen in reality. For example, if the cost of
materials goes up, the selling price is also likely to go up. However, simulation techniques (discussed later) take into consideration changes in more than one variable at a time.
* It also does not identify other possible scenarios.
* It considers the impact of all key areas (one at a time). The amount of information may overwhelm the decision maker.
* The probability of each of the assumptions is not tested.
* It only provides information to help managers make decisions. It is not a technique in itself for making a decision.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is scenario analysis?

`

A

Scenario analysis provides information on possible outcomes for the proposed investment by creating various scenarios
that may occur. It evaluates the expected value of a proposed investment in different scenarios expected in a certain
situation.
As with sensitivity analysis, the method involves calculating NPV. Unlike sensitivity analysis, scenario analysis also
calculates NPVs in other possible scenarios or ‘states of the world’. The most used scenario analysis involves calculating
NPVs in three possible states of the world: a most likely view, an optimistic view and a pessimistic view.
By changing a number of key variables simultaneously, decision makers can examine each possible outcome from the
‘downside’ risk and ‘upside’ potential of a project, as well as the most likely outcome. However, this technique has several
key weaknesses:
* as the number of variables that are changed increases, the model can become increasingly difficult and time
consuming;
* it does not consider the probability of each ‘state of the world’ occurring when evaluating the possible outcomes;
and
* it does not consider other scenarios that may occur.**

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is simulation modelling>

A

The Monte Carlo simulation method is an investment modelling technique that shows the effect of more than one variable
changing at the same time. Complex structures of capital investment are investigated through simulation techniques,
particularly modelling the impact of uncertainty. Simulation models are programmed on computers to deal with variable
factors by use of random numbers.
The model identifies key variables that drive costs and revenues (such as market size, selling price, initial investment,
changes in material prices, rates of use of labour and materials and inflation). It then assigns random numbers and
probability statistics to each variable that might affect the success or failure of a proposed project. For example, if the
most likely outcomes are thought to have a 50% probability, optimistic outcomes a 30% probability and pessimistic
outcomes a 20% probability, then a random number representing those attributes can be assigned to costs and revenues
in those proportions. These randomly selected values are used to calculate the project NPV.
Computer modelling repeats the decision many times, calculating a different NPV each time. This gives management a
view of all possible outcomes. The resulting set of NPVs can be used to show how the NPV varies under the influence of
all the variable factors. A more informed decision can then be taken depending on the management’s attitude to risk. This
approach can also be used to test the vulnerability of outcomes to possible variations in uncontrolled factors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

4 key weaknesses of simulation modelling

A
  • It is not a technique for decision making, rather providing information about the possible outcomes upon which management makes a decision.
  • It is a complex method which is not simple to calculate.
  • The time and costs involved may outweigh the benefits gained from the improved decision making.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EXPECTED NET PRESENT VALUE

A

Unlike the previous approaches, this method makes use of probabilities. In a complex world, most investment appraisal decisions are based on forecasts which are subject to uncertainties, resulting in multiple outcomes. It is imperative that these uncertainties are reflected in the investment decision. These uncertainties can be captured by assigning a probability to each outcome. The project performance is evaluated based on its expected value derived on a probability- driven cash flow.
To understand the term ‘probabilities’ or ‘probability of outcomes’, some key points are illustrated below.
* The numerical value of probability ranges between 0 to 1 and the sum of probabilities must always be exactly 1.
For example, the table below shows two scenarios of a new product being launched in the market. The result is
distributed between the probability of it being profitable (which is 0.9) and the probability of it going into loss (which is 0.1).
Outcomes Probability
Profit 0.9
Loss 0.1
Total 1.0
* Usually, the probability is estimated based on historical data or past performance trends. In the above example, the probabilities would have been derived by looking at company statistics, its past record and reputation, the trend of similar products in the market, their profitability and their success rate.
* In practice, probabilities can be subjective. Investment managers can assign different probabilities based on their experience and market research. These should be accepted if they are backed up by experience, understanding and good judgement.

======================

Expected net present value (ENPV) is a capital budgeting and appraisal technique. It is a simple tool to evaluate the feasibility of a project. It is based on net present value under different scenarios, probability weighted to adjust for uncertainties in each of these scenarios. A project with a positive ENPV will be accepted, taking the much of guesswork out of decision making. Unlike traditional NPV, ENPV produces a more realistic picture by considering any uncertainties inherent in project scenarios1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

expected value

A

The expected value is the average value of the outcome, calculated on probability estimates. The methodology is as
follows.
1. The probability of an outcome and value of that outcome is specified.
2. The expected value of each outcome is calculated.
3. All the expected values are added with each probability to arrive at the expected value.
The formula for calculating expected value is:
Expected value = ∑PX
Where:
∑ = the sum of
P = the probability of outcome
X = the value of the outcome

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Advantages & limitatipons of EV & ENVP

A

Advantages
* ENPV provides a clear ‘rule’ to aid decision making.
* The expected value and ENPV tools are simple and easy to calculate.
* A positive ENPV increases shareholder wealth if a project proceeds and outcomes follow expectations.
* ENPV provides a clear ‘rule’ to aid decision making.
* The expected value and ENPV tools are simple and easy to calculate.
* A positive ENPV increases shareholder wealth if a project proceeds and outcomes follow expectations.

Limitations
* Expected value and ENPV are measures of return. They do not take the volatility or the risk of a project into
consideration. Variability (volatility) or dispersion is measured by standard deviation.
* While ENPV takes probabilities into account, they are subjective and may be difficult to estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is standard deviation

A

Standard deviation is a statistical tool which measures the amount of variation or dispersion of a set of data from its
mean. It is a measure of risk or volatility of returns. A project can be best evaluated by measuring the standard deviation,
along with the expected value and ENPV. The higher the standard deviation, the larger the variance and the higher the
risk of a project. Standard deviation is an absolute figure. It cannot be used to compare projects unless they have the
same expected return.
Standard deviation is calculated as the square root of the variance. It measures how spread out numbers are from their
mean. Variance is the average of the squared differences from the mean.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How is standard deviation caclucated

A

Standard deviation is calculated using the steps below:
1. Deviation (d) = NPV – expected value (EV)
2. The deviation is squared (d 2 ) to remove the negative number
3. The variance is calculated as pd 2 = probability × squared deviations
4. The standard deviation (Sd) is the square root of the variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the coefficient of deviation

A

The coefficient of variation is the ratio of standard deviation to the mean (average). It measures the extent of variability or the dispersion of data points in a dataset in relation to the mean of the population.
The coefficient of variation allows comparison of different projects or investments. It can be used to compare standard deviations from projects of different sizes. While the standard deviation measures the volatility or dispersion of returns, the coefficient of variation is a better measure of the relative risk. It measures the relative dispersion of returns in relation to the expected return.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How is coefficient of deviation cacluated

A

standard deviation ÷ expected value or ENPV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are event trees and how are they constructed?

A

Event tree diagrams are a commonly used tool for risk mapping when a project or task has multiple outcomes with
different probabilities. Tree diagrams represent all possible outcomes of an event, allowing managers to calculate their probability. Each branch in a tree diagram represents one possible outcome of the project. If two events are independent, the outcome of one has no effect on the outcome of the other.
This diagrammatic approach allows all possible outcomes to be accurately mapped.

  1. An initiating event or a project that leads to further sequential events is identified (such as a product launch).
  2. The sequential events or outcomes associated with the specific scenarios are identified, building the event tree diagram.
  3. Probabilities for the sequential events (rate of success and failure) are determined.
  4. The expected value for each sequential event is calculated.
  5. The sum of all expected values gives the expected value for the project.
16
Q

Limitations of event trees

A
  • It is not normally realistic to identify the various possible outcomes and then attach probabilities to each of them.
  • Success or failure probabilities are difficult to find.
  • Event tree diagrams require an analyst with practical training and experience.
  • Event tree diagrams are not efficient where many events must occur in combination.
  • All events are assumed to be independent, which may not be always the case.
  • An initiating event is identified. The analysis is limited and dependent on one initiating event that leads to further sequential events.
17
Q

Main objectives of portfolio management

A
  • Return: the portfolio should yield steady returns that at least match the opportunity cost of the funds invested. In general, the better the growth prospects of the company, the better the expected returns.
  • Risk reduction: minimisation of risks is the most important objective of portfolio management. A good portfolio tries to minimise the overall risk to an acceptable level in relation to the levels of return obtained.
  • Liquidity and marketability: it is desirable to invest in assets which can be marketed without difficulty. A good portfolio ensures that there are enough funds available at short notice.
  • Tax shelter: the portfolio should be developed considering the impact from taxes. A good portfolio enables companies to enjoy a favourable tax shelter from income tax, capital gains tax and gift tax.
  • Appreciation in the value of capital: a balanced portfolio must consist of certain investments that appreciate in value, protecting investor from any erosion in purchasing power due to inflation
18
Q

Elements of portfolio management

A
  • The need for effective portfolio management arises once an entity builds a portfolio of investments. Effective portfolio management increases the probability of higher returns through risk reduction. Portfolio theory helps investment managers to construct portfolios that best meet the requirements of investors in terms of risk and return.
  • Portfolio management reduces risk and uncertainties through a number of strategies.
19
Q

Asset allocation overview (portfolio management)

A

Asset allocation is an investment strategy that aims to balance risk and reward by adjusting the percentage of each
asset in an investment portfolio according to the investor’s risk tolerance, goals and investment horizon.
Investments are made in suitable mix of assets according to the risk appetite or risk preferences of investors. Risk-
seeking investors can opt for more volatile assets with higher returns, while risk-averse investors look for ‘safer’ investments. For example, if an entity that manages savings of pensioners is risk averse, it will adopt a policy of investing the pension savings in government or treasury bonds to avoid the risk of losing the entire capital.

20
Q

Diversification overview (portfolio management)

A

Spreading the risk across multiple investments within an asset class is known as diversification . This is based on the well-known rule of thumb ‘don’t put all your eggs in one basket’. Effective diversification includes investments across different asset classes, securities, sectors and geography. This will not only help to boost the returns but also lower the level of risk of a portfolio.
For example, a portfolio that is comprised of only bonds carries less risk (and lower returns) than a portfolio of only equities. If the percentage of equities is increased to, say, 20%, the risk of the portfolio increases but it will also increase the potential returns. A unit trust typically spreads its funds among a large number of investments.

21
Q

Re-balancing (portfolio management)

A
  • Portfolio management is a continuous process of monitoring the performance of the portfolio, incorporating the latest market conditions and implementing the strategies in tune with investment objectives that maximises returns and minimises risk.
  • Rebalancing is this continuous process of comparing portfolio weightings with planned asset allocation.
  • Rebalancing is usually done on an annual basis. However, it can be done at any time if a significant need arises.
22
Q

Correlation (re portfolio management)

A

Correlation, in terms of portfolio management, is a statistical tool that measures the degree to which two securities move in relation to each other.
One reason for this might be that two securities have generally opposite reactions to the same external news or event.
For instance, financial stocks such as banks or insurance companies tend to get a boost when interest rates rise, while the real estate and utilities sector get hit particularly hard when interest rates increase.
Correlation is computed by using the correlation coefficient, which has a value that ranges between minus 1 and plus 1.
The correlation coefficient is a statistical measure of the strength of the relationship between the relative movements of two variables.
The values range between minus 1.0 and 1.0

23
Q

What is adverse correlation re portfolio management?

A

Negative correlation (or minus 1)
When prices move in opposite directions.
There is an inverse relationship between two variables.
Usually, the investments in industries which are dependent on each other for raw materials or services offer negative correlation. When the price of oil rises, it is likely to result in the rise of the price of an oil company’s shares ignoring other factors), but the shares of companies such as airlines are likely to fall in value.
For example, if the price of stock A increases by 5% and the price of stock Z decreases by 5% in a month, stock A and stock Z are said to have negative correlation of minus 1. When a company invests in stock A and Z at the same time, the portfolio will be constant with no change in the price (assuming the same amount is invested in both the stocks).
Essentially, gain from stock A is offset by the loss in stock Z.

24
Q

What is positive correlation re portfolio management?

A

Positive correlation (Coefficient = 1)
The correlation of investments in a portfolio is positive (or +1) when their prices move in same direction or offer same kind of return in the specified period. Usually, the investments in the same industries, or with the same set of products that can substitute each other, demonstrate positive correlation.
For example, if the price of stock A increases by 5% and price of stock Z also increases by 5% in a month, stock A and stock Z are said to have a positive correlation of +1. When a company invests in Stock A and Z at the same time, the portfolio price will increase by 5% (assuming the same amount of investment in both stocks).
The positive correlation also applies in case of falling prices. Holding both investments can dramatically increase returns but can also dramatically increase losses.

25
Q

**

What is zero correlation re portfolio management

A

Zero correlation (Coefficient = 0)
Zero correlation applies where underlying investments have no relationship that indicates any kind of correlation. Usually, investments in different asset classes or different geographic locations have zero correlation. With zero correlation, each investment performance holds the price and risk without any dependency on the performance of other investments.

26
Q

Overview - the ‘efficient frontier’ re portfolio management

A
  • The ‘efficient frontier’ is a modern portfolio theory tool that shows investors the best possible return they can expect from their portfolio for a defined level of risk. The efficient frontier aims for optimum correlation between risk and return.
  • The portfolio manager scouts for the investment opportunities which offer optimum correlation to maximise return for the portfolio.
  • The efficient frontier is curved representing a diminishing marginal return to risk.
  • Portfolios that do not provide enough return for the level of risk are considered as suboptimal (they lie below the efficient frontier).
  • Each point on the efficient frontier line represents optimal portfolio.
27
Q

Limitations of portfolio theory

A
  • It is a single-period framework.
  • Probabilities are only estimates.
  • It is based on several assumptions, including:
    – investors are risk-averse and behave rationally
    – the risk of bankruptcy, legal and administrative constraints are ignored
  • Portfolio theory assumes that the correlation between assets is constant. This may not be applicable in the real
    world as every variable is constantly changing.
  • Correlation analysis requires computation of the coefficient of each underlying security. It is very complex in terms of gathering historical numbers, model selection and calculating with accuracy.
  • The theory does not assume any tax payouts or legal and administrative costs. These are essential factors in
    determining investment decisions.
  • The theory ignores the timeframes (short term, medium term or long term) of the investments. Return expectations may change depending on these timeframes. Some randomly selected portfolios may have performed better than optimally selected portfolios, at least for a short time.
  • Despite the availability of software programs to perform the calculations, the portfolio model is still not widespread as portfolio managers are sceptical about the accuracy of the forecast data. They may prefer to use their own judgement in selecting investments.