Chapter 13 Flashcards

1
Q

What is a Project Monitoring system?

A

A system for determining what data to collect, analyzing that data; and reporting current progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The percent complete index actual costs assumes the ____________ is (are) the most reliable information for measuring percent complete.

A

actual costs-to-date and expected cost at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The percent complete index budgeted costs, with regard to the first index, assumes the ____________ is (are) the most reliable information for measuring percent complete.

A

original budget of work complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is included in creating the project Baseline?

A
  1. Labor
  2. Materials
  3. Equipment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Frequently budgets are ______ - ______ for materials and labor separately for more effective control over costs.

A

Time-Phases

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A SPI value less than one indicates that the project is

A

Behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which formula will calculate the estimated total cost at completion for a project?

A

AC + ETCre

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly