Chapter 12 Flashcards

1
Q

The key to brainstorming is separating the ____ from the ____

A

Inventing, deciding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the Politician role concerned with as a PM?

A

Understand diverse cultures of parent and client organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the Friend role concerned with as a PM?

A

Determine the important relationships to build and sustain outside the team itself.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the Marketer role concerned with as a PM?

A

Understand the strategic objectives of the client organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the Coach role concerned with as a PM?

A

Motivate client team members without formal authority.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A synonym for a “fixed-price contract” is

A

Lump-Sum Agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The purpose of a contract change control system is to

A

define the process for changing the original contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the final step in the RFP process?

A

Select the Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the first step in the RFP process?

A

Summary of needs and request for action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Who bears the majority of the risk in a fixed-price contract?

A

The contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A change to a project and/or contract is called a…

A

change order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What type of negotiation emphasizes collaborative problem solving?

A

Principled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the possible negative effect of contracts in terms of innovation?

A

They can hurt improvements and innovation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Project managers must be skilled at managing customer…

A

Expectations and Perceptions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the six steps of Procurement Management?

A
  1. Planning purchases
  2. Planning contracting
  3. Requesting seller responses
  4. Selecting sellers
  5. Administering the contract
  6. Closing the contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Contracts with long lead times such as construction and production projects may include…

A

Escalation Provisions (cost of materials)

17