Ch.15 Flashcards
According to Nfpa 1911 fire pumps of 1250 gpm capacity must achieve prime in ________ seconds or less?
30 seconds or less
Testing hose if the scribe mark is found to have moved away more than ______ inches from the coupling , stop the test and replace the hose?
3/8ths inch
I’m jurisdiction’s that are higher than 2000 feet above sea level , a _____________ test should be performed as part of the acceptance testing?
Pumping engine overload
The pump body as well as the entire intake and discharge piping system with the exception of the tank fill and the tank to pump lines on the tank side of the valves are subjected to a minimum hydrostatic test pressure of ?
500 psi
Pumpers with an onboard tank capacity of _______ gallons or less must be capable of flowing _____ gpm from onboard tank?
500 gallons
250gpm
What are the 4 pressures used when doing a performance test for a pump?
150gpm
165 gpm
200 gpm
250 gpm
According to NFPA fire pumps of 1500 gpm rating must be primed with in ______ seconds?
45 seconds
When pump testing , if the pump fails to reach ____ of mercury, remove the apparatus from service until repairs can be made?
22 inches
The two basic categories of testing are grouped as _________ and ______________ tests?
Pre service and performance tests
Testing method that uses water under pressure to check the integrity of pressure vessels ?
Hydrostatic test
Pre service apparatus maneuverability tests designed to determine the road worthiness of a new vehicle ?
Road test
The apparatus must accelerate to ___ mph from a standing start with in 25 seconds , tested in two runs in opposite directions?
35mph
Apparatus must achieve a maximum top speed of ____ mph during a road test?
50 mph
During a road test the apparatus must come to a full stop from 20 mph within ____ feet ?
35 feet
During the hydrostatic test the apparatus is subjected to 500 psi for a minimum of ___ minutes?
10 min