Ch.15 Flashcards

1
Q

According to Nfpa 1911 fire pumps of 1250 gpm capacity must achieve prime in ________ seconds or less?

A

30 seconds or less

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Testing hose if the scribe mark is found to have moved away more than ______ inches from the coupling , stop the test and replace the hose?

A

3/8ths inch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

I’m jurisdiction’s that are higher than 2000 feet above sea level , a _____________ test should be performed as part of the acceptance testing?

A

Pumping engine overload

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The pump body as well as the entire intake and discharge piping system with the exception of the tank fill and the tank to pump lines on the tank side of the valves are subjected to a minimum hydrostatic test pressure of ?

A

500 psi

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Pumpers with an onboard tank capacity of _______ gallons or less must be capable of flowing _____ gpm from onboard tank?

A

500 gallons
250gpm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the 4 pressures used when doing a performance test for a pump?

A

150gpm
165 gpm
200 gpm
250 gpm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

According to NFPA fire pumps of 1500 gpm rating must be primed with in ______ seconds?

A

45 seconds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When pump testing , if the pump fails to reach ____ of mercury, remove the apparatus from service until repairs can be made?

A

22 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The two basic categories of testing are grouped as _________ and ______________ tests?

A

Pre service and performance tests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Testing method that uses water under pressure to check the integrity of pressure vessels ?

A

Hydrostatic test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Pre service apparatus maneuverability tests designed to determine the road worthiness of a new vehicle ?

A

Road test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The apparatus must accelerate to ___ mph from a standing start with in 25 seconds , tested in two runs in opposite directions?

A

35mph

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Apparatus must achieve a maximum top speed of ____ mph during a road test?

A

50 mph

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

During a road test the apparatus must come to a full stop from 20 mph within ____ feet ?

A

35 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

During the hydrostatic test the apparatus is subjected to 500 psi for a minimum of ___ minutes?

A

10 min

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

__________________ is conducted to demonstrate to the purchaser that the apparatus confirms to all bud specifications at the time of delivery?

A

Acceptance testing

17
Q

For pumper performance testing the barometric pressure should be Atleast ____?

A

29 inches of mercury

18
Q

The air temperature when pumper performance testing is conducted should be between ___ and _____ degrees ?

A

0° and 110° F 

19
Q

A _________ with a knife edge and air chamber rated from 0 to at least 160 psi is required if a flowmeter is not used?

A

Pitot tube

20
Q

The difference in readings between the flowmeter and pitot guate must not be more than ____%?

A

10%