A project

A

A series of related jobs usually directed toward some major output and requiring a significant period of time to perform.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project mgt

A

defined as planning, directing, and controlling resources (people, equipment, material) to
meet the technical, cost, and time constraints of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Organizational structures for PM

A

Pure Project: where a self-contained team works full time on the project.
Functional Project: where team members are assigned from functional units of the organization. can work on other projects too
Matrix project : blend of pure and functional structure. the Pm manager decides what task and when they will be performed, the functional manager controls the people and tech used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Steps of a project

A

-A project starts outas a statement of work
a task is a subdivision of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Gantt Chart

A

sometimes referred to as a bar chart, showing
both the amount of time involved and the sequence in which activities can be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Earned Value Management

A

Technique that combines measures of scope, schedule, and cost for evaluating project progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Critical Path Method

A

used to determine the project duration, tasks are critical - for repetitive type of projects(no uncertainty)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Types of Project mgt

A

Waterfall(Trad)- widely used progress flows steadily downwards & project implemented at the end when completely finished
Agile (Scrum)- Iterative(repitition) progress and project is gradually implemented

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What type of Project Mgt addresses complex adaptive problems

A

Agile(scrum)- heavily used in software development

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Categories of Projects

A

Conventional(Low-Tech)
Innovative (High-Tech)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

PM Triangle about

A

Schedule, cost & scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a tool used for

A

Help manage changes during project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Work Breakdown Structure (WBS)

A

Hierarchical breakdown of the tasks required to accomplish a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Project Scheduling occurs before the WBS is complete

A

False it occurs after

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Activity, event, milestone

A

-A task that consumes time &resources
-A point in time that rep the start & end of 1/more activities
-An event of major significance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Project Scheduling Tools

A

Tasks- in circles
Arrows show sequence

16
Q

Critical Path

A

sequence of activities that requires longest total time from start to finish(you can have more than 1)

17
Q

Slack Formula

A

Slack= Latest Start - Earliest Start
Slack= Latest Finish -Earliest Finish
diff. bet latest vs earliest