Ch 4 - Schedule Planning Flashcards
define activity definition
identifying the activities of the project that need to be performed to produce the product or service of the project
define activity duration
assessing the number of work periods needed to complete the project activities.
Work periods are usually expressed in hours or days.
Large projects might express duration in weeks or months.
define activity list
a list of all the activities required to complete the work of the project that also includes an identifier code and the WBS code it’s associated with. Activities are broken down from the work package level of the WBS
define activity sequencing
sequencing activities in logical order and determining whether dependencies exist among the activities
define analogous estimating or top-down estimating
estimating technique that uses the actual duration of a similar, completed activity to determine the duration of the current activity.
define backward pass
calculating the start and late finish dates by starting at the end of a network diagram and working back through each path until reaching the start of the network diagram. Part of the critical path method (CPM)
define critical path method (CPM)
- mathematical technique to develop the project schedule
- schedule development method that determines a single early and late start date, early and late finish date, and the float for each activity on the project
define crashing
schedule compression technique that adds resources to the project to reduce the time it takes to complete the project
define critical path (CP)
longest path through the project.
activities with zero float are considered critical path tasks.
define dependencies
relationship between project activities
define dependency relationships
type of dependency between two activities and the specific relationship between the activities
define document control process
defines how revisions are made, version numbering system, and placement of the version number and revision date
define duration compression
use of techniques such as fast-tracking or crashing to shorten the planned duration of a project or to resolve schedule slippage
define early finish
earliest date an activity may finish as logically constrained by the network diagram
define early start
earliest date an activity may start as logically constrained by the network diagram
define external dependency
type of dependency where relationship between a project task and a factor outside the project (weather conditions, outside contractor) drives scheduling of that task
define finish-to-finish
project task relationship in which the finish of the successor task is dependent on the finish of the predecessor task
define finish-to-start
project task relationship in which the successor task cannot begin until the predecessor task has completed
define float time or slack time
amount of time the early start of a task may be delayed without delaying the finish date of the project
define forward pass
process of working from left to right of a network diagram in order to calculate early start and early finish dates for each activity
define iterative process
- any process that is repeated more than once.
- five process groups are repeated throughout the project’s life because of change requests, responses to change, corrective action, and so on.
define late finish
latest date an activity can complete without impacting the project end date
define late start
latest date an activity can start without impacting the project end date
define logical relationships
dependency relationship that may exists between