Two types of concrete spalling are experienced during fires? Pg 217
Explosive spalling, which propels concrete downward with an explosive force and is accompanied by a loud noise and a dropping spalling , which is similar to plaster ceiling collapse.
The construction industry uses two different types of framework for high rise structures? Pg 216
Reinforced concrete and structural steel.
The laws in some states require that, when high rise buildings under construction exceed 150 feet or 15 stories what is needed? Pg 223
An outside stem and yoke control valve (OSY) must subdivide the vertical pipe riser into sections.
How many sides of the building does the EPA require be enclosed when asbestos is present and demolition is being performed? p. 222
All four
Which type of strength does the concrete give the structure? p. 216
Compressive
What do some states require when a building under construction is over 15 stories in height? p. 223
Outside stem and yoke control valve
How many floors at a time can have the asbestos scraped, packaged and taken away? p. 222
One
What makes the formwork fire (even without concrete pouring) a dangerous one to operate at? p. 219
Use of very few nails
Approximately how many days does it take for concrete to reach its maximum strength? p. 216
27 days
What often ignites the nearby wood or plastic sheeting when concrete floors are curing? p. 218
Heaters
In which of the following structures are more firefighters killed? p. 215
Buildings under construction
How many lengths of folded hose must the firefighter carry to the floor below the fire in a building under demolition? p. 222
Four
What will be the major cause of fire extension in a framework fire in a cast-in-place building under construction? p. 220
Burning timbers
Which of the following does NOT occur due to the protective measures taken when removing asbestos from a
building? p. 222
Create a cross breeze within the building
What is the minimum distance that a shanty must be located from the building under construction? p. 218
30 feet (9 m)