What structural element is used to check compliant elevation on Zone V structures?
A
Lowest Floor Elevation (LFE)
2
Q
Which process allows an applicant to have his or her rejected permit application be reviewed by an independent board?
A
Appeal
3
Q
Which Flood Insurance Study (FIS) graph displays the base flood elevations (BFEs) for 500-year, 100-year, 50-year, and 10-year floods for a river or stream?
A
Flood Profile
4
Q
Which area on a flood map may require that a base flood elevation (BFE) be developed before a permit for a structure can be issued?
A
Approximate Zone A
5
Q
How many acres or parcels have to be inundated to be eligible for a flood insurance claim?
A
1 acre or 1 property