CE Mix2 Flashcards
What must accompany a fire and smoke damper as part of this fire protection feature?
Labeled access point.
The labeled access point must be large enough to provide access for inspection and maintenance.
What should an architect do if the shop drawings are different from the proposed contract documents?
Note the deviation of the detail and bring it to the attention of the consultant.
According to AIA A101, the owner has how many days after the issuance of the architects final certificate of payment to pay it?
30 days
Per AIA A101
For which of the reasons would the contractor consider using the alternate, fly ash, in lieu of portland cement?
- Lower embodied energy-
Because fly ash is a byproduct of burning pulverized coal, it requires less energy to produce than portland cement. It also requires less water than portland cement. - Better workability-
Fly ash improves the segregation of the concrete, thereby making it easier to pump. These added benefits would lead to a quicker slab pour.
If the proposed product or method by a subcontractor or contractor is different from the product or method in the specifications, what is the architect to do?
The subcontractor and contractor should follow specifications unless directed by the owner to do something different. Owners approve and give directives. Architects merely review for compliance.
Architects don’t approve submittals, architects review them for compliance with the contract documents !!!!
According to AIA A201, the Contractor is required to add which parties to its commercial liability policy to protect against claims caused by the Contractor’s negligent acts or omissions during the Contractor’s operations?
Owner
Architect
Architects Consultants
True or False?
Addenda are included in the Bid Documents.
True
Addenda can be issued prior to or during the bidding phase.
When the term “day” is used in the AIA A201 General Conditions, how it is defined?
Day = Calendar Day
all days including weekends and holidays
What is the “New Rules of Measurement Document”?
New Rules of Measurement (NRM1) :
provides guidance on the quantification of building works for the purpose of preparing cost estimates and cost plans. Direction is also given on quantifying other construction project costs which are not reflected in the measurable building work items: preliminaries, overheads and profit, project team and design team fees, risk allowances, inflation, and other development and project costs.
What is a ProForma?
It is an analysis of the building project showing costs and return on investment.
A proforma analysis is a set of calculations that projects the financial return that a proposed real estate development is likely to create. This report is typically done by the client at the beginning of the project to determine if the project will be profitable.
What is a “General Obligation Bond”?
Shareholders are guaranteed to be repaid using future tax revenues. Bonds are backed by the credit and taxing power of the issuing jurisdiction rather than the revenue from a project.
When are Performance Bonds and Payment Bonds issued from the Contractor to the Owner?
Before work begins on site.
True or False:
The services required to document alternates in the Bidding documents is a basic Service of the Architect according to AIA B101.
False-
“Perpetration of design and documentation for bid alternates or proposal requests by the owner” are under additional services in the contract.
Builders Risk Insurance is purchased by the owner and is also called what?
ALL RISK
All risk insurance covers fires (specific peril), theft, vandalism, and malicious mischief.
True or False:
Abbreviations should be consistent with drawings when used in a Specification Manual.
FALSE
Abbreviations should NOT be used at all in specifications !!!
True or False:
Smoke detectors can be installed on walls.
True.
They can be installed on the ceiling or the wall, but they must be a minimum of 4” from a perpendicular surface to be out of the dead-air space zone.
What must also be installed if there is not an operable window in a residential bathroom?
Mechanical Fan
Glazed openings are not required if mechanical ventilation is installed and ducted direct to outside, min. 50 CFM intermittent or 20 CFM continuous.
When does the Architect’s Contract Administration responsibilities begin?
After the award of the construction contract.
What is the difference between “Construction Administration” and “Contract Administration”?
Construction Administration and Contract Administration are terms that are used interchangeably in the profession.