CDT Flash Cards 10
1
Q
- The Procurement Requirements usually include:
A. Invitation or Advertisement to Bid, Instructions to Bidders, Information Available to Bidders, Bid Forms and Attachments, and Bid Security Forms
B. Instructions to Bidders, Information Available to Bidders, Bid Forms and Attachments, and Bid Security Forms
C. Instructions to Bidders, Information Available to Bidders, Bid Forms and Attachments, Bid Security Forms, Conditions of the Contract, Specifications, and Drawings
D. All the documents necessary to bid the project
A
A. Invitation or Advertisement to Bid, Instructions to Bidders, Information Available to Bidders, Bid Forms and Attachments, and Bid Security Forms
2
Q
- The contract type most often associated with the term “turkney” is called:
A. Construction management
B. Project management
C. Design-Build
D. Owner-Builder
A
C. Design-Build
3
Q
- The “Work” required of the Contractor by the Contract Documents is defined to include:
A. Labor and materials
B. In-place construction
C. Services of the Contractor
D. Construction and services, whether completed or partially completed:
A
D. Construction and services, whether completed or partially completed
4
Q
- Unless otherwise stipulated, allowances cover:
A. Materials and equipment delivered
B. Materials and equipment delivered, plus unloading and handling at the site
C. Materials and equipment delivered, plus Contractor’s overhead and profit
D. Materials and equipment delivered and installed:
A
A. Materials and equipment delivered
5
Q
- If a shop drawing is submitted by the Contractor and stamped “approved” by the Architect, who is responsible for any deviations from the Contract Docuements shown on the shop drawing?
A. A/E
B. Owner
C. Contractor
D. A/E and Contractor:
A
C. Contractor
6
Q
- Disputes arising out of or related to the Contract are subject to:
A. Mediation
B. Arbitration
C. Mediation followed by arbitration
D. Arbitration followed by litigation if the parties cannot agree:
A
C. Mediation followed by arbitration
7
Q
- A Construction Change Directive must be signed by:
A. Owner
B. Owner and A/E
C. Owner and Contractor
D. Owner, A/E, and Contractor:
A
B. Owner and A/E
8
Q
- The decision on the amount of information to include in a section (i.e., a level two, a level three, or a lever four specification section), is based on all of the following reasons, EXCEPT:
A. Complexity of the project
B. The scope of work included in the section
C. Local trade jurisdiction
D. Length and complexity of a section:
A
C. Local trade jurisdiction
9
Q
- A statement that establishes the precedence of the various contract documents to be considered when a conflict occurs is located in the General Conditions document A201:
A. True
B. False:
A
B. False
10
Q
- A listing of Owner-furnished Contractor-installed items is located in:
A. Part 1, General, Summary of Work
B. Division 01
C. Part 2, Products, Product Requirements
D. Part 3, Execution, Execution Requirements:
A
C. Part 2, Products, Product Requirements
11
Q
- Administrative procedures and descriptions for allowances and unit price work are located in:
A. Part 1 - General
B. Division 01, Price and Payment Procedures
C. Part 3, Execution, Execution Requirements
D. Both A & B:
A
D. Both A & B
12
Q
- An allowance:
A. Is a dollar amount that the bidder includes in the bid to cover the cost of items to be determined at a later time
B. Is a specified quantity of a product that the bidder includes in the scope of work, even though the location is not indicated on the Drawings
C. Must be accompanied by a unit price quote in order to equitable adjust the contract price later
D. Can be either a dollar amount that the bidder includes in the bids, or a quantity of a product along with a unit price that the bidder includes int he scope of work:
A
D. Can be either a dollar amount that the bidder includes in the bids, or a quantity of a product along with a unit price that the bidder includes int he scope of work
13
Q
- Unit prices are addressed in which part of the Project Manual?
A. Bid Form
B. Division 01, General Requirements
C. Technical Specifications
D. All of the above:
A
D. All of the above
14
Q
- All of the following are true regarding unit prices EXCEPT:
A. Unit prices should not be used when lump-sum bids are requested
B. Unit prices are useful when the nature of the work is defined, but the extent is not known
C. Unit prices can be different for an “add” cost than for a “deduct” cost
D. The Bid Form should include a schedule for units prices with the A/E’s estimate of quantity:
A
A. Unit prices should not be used when lump-sum bids are requested
15
Q
- Substitutions proposed during the bidding phase of a project:
A. Allows bidders to propose for specified products that are no longer available or not available in time to meet the project schedule
B. May require additional time for the A/E to evaluate prior to taking bids
C. Allows for the introduction of a possible superior or more cost-effective product than the one specified
D. All of the above:
A
D. All of the above