CDS Flashcards

0
Q

Allows the CM to charge the owner the actual construction cost of the project plus a negotiated fee that is agreed to before construction begins

A

Cost-plus structure

Actual costs are typically determined by the lowest bid received from the managers subcontractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Allows manager to establish a guaranteed cost of construction (including managers services) before design is fully documented

A

Fixed-price structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The highest probable cost limitation for the construction of the project guaranteed by the construction manager

A

Guaranteed maximum price structure

Any cost savings from a positive bid climate go to the owner not the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Buildings designed after the original building that are either substantially similar to or modifications of the original buildings

A

Derivative works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A civil wrong that causes injury to another person

A

Tort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

requirements for bidding and contracting including bid solicitation, instruction to bidders, bid forms, bonds and certificates, general condition of contract

A

Division 00

procurement and contracting requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

requirements that are applicable to entire project, summary of work, alternates, unit prices, submittal procedure, pricing and payment

A

Division 01

General requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

site remediation, site decontamination, subsurface investigation, surveying, selective demolition

A

Division 02

Existing conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

forms, reinforcement, cementitious deck and underlayment, grouts, restoration and cleaning

A

Division 03

Concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

brick, concrete block, stone, terra cotta, glass block

A

Division 04

Masonry

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

structural steel, metal fabrication, ornamental ironwork, handrails, expansion joint covers

A

Division 05

Metals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

structural wood framing, rough carpentry, finish carpentry, structural plastics

A

Division 06

Wood, plastics, and composites

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

dampproofing and waterproofing, insulation, vapor retarders, air barriers, shingles, roof tiles, siding, flashing, joint sealers, fire and smoke protection, roofing specialties

A

Division 07

Thermal and moisture protection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

metal doors and frames, wood doors and frames, specialty doors, storefronts, windows, skylights, hardware, curtain walls

A

Division 08

Openings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

plaster, gypsum wallboard, floor and wall tile, flooring materials, acoustical ceilings, light-gage metal framing paritions

A

Division 09

Finishes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

toilet compartments, visual display boards, louvers, grilles, flagpoles, lockers, awning, toilet and bath accessories

A

Division 10

Specialties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

vaults and security items, church related equip, library equip, theater and stage equip, musical equip, audio-visual equip, loading dock equip

A

Division 11

Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

furniture, system furniture, art, window treatments

A

Division 12

Furnishings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

special-purpose rooms (clean room / saunas), radiation protection, lightning protection, pre-engineered structures

A

Division 13

Special construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

elevators, escalators, dumbwaiters, moving walks, lifts

A

Division 14

Conveying equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

fire suppression systems, wet-pipe, dry-pipe, standpipes and hoses

A

Division 21

Fire Suppression

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

plumbing for buildings

A

Division 22

Plumbing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

HVAC

A

Division 23

Heating, Ventilating, and Air Conditioning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

energy monitoring and control, environmental control, lighting control

A

Division 25

Integrated Automation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

electrical

A

Division 26

Electrical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

communication, sound, video

A

Division 27

Communication

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

intrusion detection, security access, video surveillance

A

Division 28

Electronic safety and security

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

excavation and fill, grading, soil stabilization, erosion control, foundation walls, caissons, piles

A

Division 31

Earthwork

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

above grade items like paving, fences and gates, site furnishings

A

Division 32

Exterior improvements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

water distribution, sanitary piping, septic tanks, subdrainage, storm drainage

A

Division 33

Utilities

30
Q

Standard form of agreement between Owner and Contractor

A

A101

31
Q

General conditions of the contract for construction

A

A201

32
Q

Standard form of agreement between contractor and subcontractor

A

A401

33
Q

Guide for supplementary conditions

A

A503

34
Q

Instructions to bidders

A

A701

35
Q

Standard form of agreement between owner and architect

A

B101

36
Q

Standard form of architect’s services: design and construction administration

A

B201

37
Q

Standard for of architect’s services: programming

A

B202

38
Q

Joint venture agreement for Professional services

A

C101

39
Q

Standard form of agreement between architect and consultant

A

C401

40
Q

Standard form of agreement between owner and contractor: construction manager as Advisor

A

A132

41
Q

standard form of agreement btw owner and construction manager as constructor where the basis of payment is the cost of work plus a fee with a guaranteed maximum price

without a guaranteed maximum price

A

A133

A134

42
Q

Agreement between owner and design-builder

A

A141

43
Q

Standard form of agreement between design-builder and architect

A

B143

44
Q

standard form of agreement between owner and contractor for integrated project delievery

A

A195

45
Q

standard form of agreement between owner and architect for integrated project delivery

A

B195

46
Q

in all windowsill details, the glass is placed on two or more _______ to support the weight of the glass and cushion it from the frame

A

setting blocks

47
Q

used in window jamb frames to prevent the glass from touching the jambs

A

anti-walk blocks

48
Q

a material used to cushion and seal the glass against the stop and the frame

A

glazing bead

49
Q

a removable piece used to hold the glass in place after it has been installed in the frame, which makes it possible to replace the glass when necessary

A

stop

50
Q

requires a project architect or designated quality control reviewer to check the work immediately before it is distributed to the user

A

Quality control

51
Q

requires periodic checks of the work while it is being developed. periodic check sets generated for the reviewer when the project is 25%, 50% and 90% complete

A

quality assurance

52
Q

goes beyond quality control and quality assurance

A

total quality management

53
Q

not part of the contract documents, but may be included in the project manual and be designated “for information only”

A

subsurface soil conditions report

54
Q

procedures for submittals are found in which masterformat division

A

01

general requirements

55
Q

requirements for testing of materials and equipment are in which part of each technical section of the masterformat system

A

Part 3

56
Q

type of specification that requires a material or product to comply with the requirements of an independent testing laboratory or authority

A

reference specification

57
Q

Coverage insures the owner in the event that use of the property is lost

Not required by A201

A

Loss of use insurance

58
Q

Permits authorized by the code official in the project jurisdiction

A

Occupancy permit

Architects do not issue occupant permits

59
Q

Type of construction: non combustible materials

A

Types I and II

60
Q

Type of construction: exterior walls non combustible, interior elements are any materials complying with code

A

Type III

61
Q

Type of construction: heavy timber construction

A

Type IV

62
Q

Type of construction: exterior and interior elements are of any materials complying with the code

A

Type V

63
Q

Allow the architect to confirm that the design intent and requirements of the construction documents will be met by the products that the contractor proposes to include

A

Submittals

64
Q

Where there are more than 6 separate-sex water closets how many must be accessible

A

Half of those provided (at least one)

65
Q

A small area subsidiary to the primary occupancy of the building in which it is located

A

Accessory occupancy

66
Q

Who should prepare the owner-contractor agreement, including the general conditions

A

Owner’s attorney

Architects are not permitted to prepare contracts to which they are not a party

67
Q

What do the contract documents consist of

A

Agreement between owner and contractor, conditions of the contract (general and supplementary conditions), drawings, specifications, addenda

68
Q

Bid amounts must be expressed in which ways? Which one prevails?

A

Bid amounts must be expressed in the bid form in both words and numerical form. If there is s discrepancy between the two, the words prevail

69
Q

Sheet type designators (0-9)

A
0 schedules, keynote legend, general notes
1 plans
2 elevations
3 sections
4 large scale views
5 details
6 schedules and diagrams
7 user defined
8 user defined
9 3D representations
70
Q

Quasi-judicial

A

An architects interpretations of the contract documents are performed in a quasi judicial capacity

Will not show partiality to either the owner or contractor

71
Q

A305

A

Contractors qualification statement

72
Q

Labor and material payment bond

A

Guarantee payment for labor and materials

Protects the owner against possible liens against the property