CDM REGULATIONS Flashcards

1
Q

Risk assesmnets

A
Identify
Determine who could be at risk
Assess risks
Evaluate control measures
Record
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Role of the Principle Designer

A
PLAN    MANAGE  COORDINATE
Reduce all foreseeable risks
Liaise with Designers
Construction Phase
Reduce risks during use and demolition of the site
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Need for a Principle Designer

A

When works involve two or more contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Regulatory basis for HSE in construction

A
Heath and safety at work act 1974
S2 - 
S6 - 
Regs
Management of Health and Safety at Work Regulations 1999
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who are the three main duty holders

A

Contractor, Designer and Operatives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CDM REQUIREMENTS

A

20 or more operatives on site at a given point in time
30 or more construction days
500 person days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly