Carpentry Exam #4 Flashcards
A 9m extension ladder is extended 6.83 m up the side of a wall. How far
should the base of the ladder be from the wall?
a. 1.7m
b. 1.4m
c. 2.2m
d. 2.3m
a. 1.7m
What is the proper connection for fire detectors?
a. parallel
b. series
c. daisy chain
d. all of the above
a. parallel
When new materials are received on a job site, what is to be done with the material safety data sheet (MSDS)?
a. Tape it to the container(s)
b. Read and discard
c. Give it to the supervisor
d. Place it in the on-site MSDS file folder
d. Place it in the on-site MSDS file folder
. A permit is required to be taken out?
a. within 48hrs of completing a job
b. within 48 hours of commencing work
c. before commencing work
d. within 72 hours of job completion date
c. before commencing work
Why can’t a shackle pin not be replaced with a nut and bolt?
a. nut and bolt may come apart
b. nut and bolt may not be hard enough
c. metal is dissimilar
d. the pressure of the nut and bolt will break the shackle when tightening
b. nut and bolt may not be hard enough
Where is the lanyard attached when erecting scaffolds?
a. above the head
b. below the shoulders
c. below the waist
d. below the feet
a. above the head
Which fasteners are used on polyurethane insulation?
a. fiber tape
b. foil tape
c. stainless steel wire
d. aluminum banding
a. fiber tape
How many bands are needed on an 18 in. × 3 in. iron pipe insulation
measuring 96 ft. long, with bands on each end and at 9-in centers?
a. 129
b. 130
c. 131
d. 125
a. 129
What size of 4-oz. canvas is required to cover a 100 mm × 25 mm iron pipe
90° elbow?
a. 500 mm × 500 mm
b. 450 mm × 450 mm
c. 550 mm × 550 mm
d. 400 mm × 400 mm
b. 450 mm × 450 mm
Which procedure ensures that air enters an asbestos removal enclosure
safely?
a. Use perforated tape on wall seams and overlap floor seams to seal air.
b. Seal all joints to ensure air flow enters only at transfer doors.
c. Tape only the horizontal seams and overlap vertical seams to allow air
passage.
d. Install positive air pressure fans at inlet and tape all seams.
b. Seal all joints to ensure air flow enters only at transfer doors.
A 100-ft. long curtain wall with a 3- in. space is to be fire-stopped with
self-leveling caulking to a depth of 2 in. How much material is required to fill
the void?
a. 4.16 cu. ft.
b. 3.20 cu. ft.
c. 50.60 cu. ft.
d. 41.60 cu. ft.
a. 4.16 cu. ft
Which chisel is used to remove deteriorated mortar joints in restoration
work?
a. pointing
b. plugging
c. brick set
d. cold
b. plugging
What is the procedure to mixing a muriatic acid solution for cleaning
brick?
a. Mix the soapy water solution into the acid.
b. Mix the acid into the soapy water solution.
c. Mix the acid into the water.
d. Mix the water into the acid.
c. Mix the acid into the water.
How is the insulation installed when installing rigid insulation in a cavity
wall system?
a. With a 25-mm air space.
b. Tight to the exterior wall.
c. With a 50-mm air space
d. Tight to the back up wall.
d. Tight to the back up wall.
Which type of fastener should be used when attaching wall ties to a wood frame structure?
a. Machine screw.
b. Wood screw
c. Carriage bolt
d. nail
b. Wood screw
Which chisel is used for dressing the stone edges?
a. pitch
b. comb
c. plug
d. point
a. pitch
Chimney liners must extend at what minimum height above the chimney
cap?
a. 50mm
b. 30mm
c. 40mm
d. 60mm
a. 50mm
This type of trap is not permitted in a drainage system?
a. S trap standard
b. bell trap
c. P trap
d. drum trap
b. bell trap
Asbestos cement pipe installed below a 60 mm thick concrete floor must
be at least how deep?
a. 600m
b. 400m
c. 550m
d. 200m
a. 600m
Which manufacturing method produces the strongest pipe?
a. extruded
b. butt weld
c. lap weld
d. spiral weld
a. extruded