CAPM Formulas Flashcards
1
Q
Planned Value
A
PV = percent complete of where the project should be
2
Q
Earned Value
A
EV = percent complete * BAC
3
Q
Cost Variance
A
CV = EV - AC
4
Q
Schedule Variance
A
SV = EV - PV
5
Q
Cost Performance Index
A
CPI = EV / AC
6
Q
Schedule Performance Index
A
SPI = EV / PV
7
Q
Estimate at Completion (typical variance)
A
EAC = BAC / CPI
8
Q
Estimate at Completion (atypical variance)
A
EAC = BAC + AC - EV
9
Q
Estimate at Completion
A
EAC = AC + ETC
10
Q
Estimate to Complete
A
ETC = EAC - AC
11
Q
To-Complete Performance Index (BAC)
A
TCPI = (BAC - EV) / (BAC - AC)
12
Q
To-Complete Performance Index (EAC)
A
TCPI = (BAC - EV) / (EAC - AC)
13
Q
Variance at Completion
A
VAC = BAC - EAC