CalGreen Flashcards
When is it necessary to do Storm Water Pollution Protection in CalGreen?
projects that disturb less than one acre
How many bicycle parking spaces are required?
2 spaces minimum or 5% of parking
How many clean air vehicles are required?
1-2 spaces per 25 total
How many electric vehicle charging is required?
1 for 10 or 1 per 25
How much water should each tenant consume if required to have its own submeter?
expected to consume 100gal/day
How much sf is required to have outdoor water use standards?
areas over 500 sf
How much construction waste must be recycled?
65%
When is commissioning required?
buildings over 10,000 sf
What type of air filter should be used in HVAC construction?
MERV8
How far away from a building must you be for tobacco smoke control?
no smoking within 25 feet of building openings or intake
HVAC refrigeration and fire suppression shall not contain_____
Halons
What is the max gallons per flush for water closets?
not exceed 1.28 gal/flush
What is the max gallons per flush for urinals?
not exceed 0.5 gal/flush
What is the max gallons per flush for showerheads?
not exceed 2.0 gal/minute
When do you need commissioning?
for new buildings greater than 10,000sf