A201 Flashcards
1
Q
who pays for the building permit?
A
contractor
2
Q
what are examples for when a warranty doesn’t apply?
A
damage from abuse, alterations not in contract, improper maintenance, normal wear and tear
3
Q
who buys the materials?
A
contractor
4
Q
how long until owner has the right to carry out the work?
A
10 days
5
Q
how long does contractor have to give notice of unknown/concealed conditions?
A
21 days
6
Q
how long does architect and owner have to review the superintendant?
A
14 days
7
Q
When is the architect’s duty to administer the contract complete?
A
It terminated when architect issues the final certificate for payment
8
Q
The Initial Decision Maker will review claims between the Owner and Contractor within ____ days.
A
10