C9.2 CDM documentation Flashcards
Preconstruction information overview
info for those bidding for work
provides H&S info to be taken into account when tendering
use to assess each tender
info for construction phase plan
preconstruction info sources
client provides info to other duty holders
principal designer helps
designers take info into account when preparing designs
preconstruction information content
relevant to project, appropriate detail, proportionate to level of risk
info affecting site
info affecting construction work
info ref proposed use of structure
existing H&S file info
description of project - client brief, construction dates
planning & management
managing H&S on site
preconstruction info - planning & management
arrangements for planning & managing construction allocation of resources / time arrangements for coordination / cooperation site security site welfare H&S requirements site activities adjacent activities security arrangements
managing H&S on site - safety hazards
site boundaries restrictions ref deliveries storage of hazardous items location of existing services ground conditions existing structures - stable / fragile difficulties, eg damaged structures
managing H&S on site - health hazards
asbestos hazardous items contaminated land existing structures health risks from activities on site
construction phase plan - purpose
sets out how H&S risks will be managed during construction
site rules
control of specific risks, eg near HV
who produces construction phase plan
principal contractor
construction phase plan content
description of project details of parties involved management structure and responsibilities of parties to project H&S standards how H&S risks will be communicated how contractors selected accident reporting arrangements welfare arrangements H&S training inc induction consultation arrangements with workers site rules RA & SSWs emergency arrangements monitoring arrangements arrangements for specific risks, eg w@h
H&S file - purpose
only for project where more than one contractor
source of info for future construction, alteration, refurb or demolition
H&S file - preparation
responsibility of principal designer
continual process throughout project
inc details of what info needed / format at tender stage
relevant info passed to principal designer
H&S file - contents
description of work carried out
hazards eliminated through design / construction
key structural principles
SWLs of floors / roofs
hazardous materials used
info ref dismantling / removal of installed plant / equipment
H&S info ref plant maint
location of services, eg underground cables, gas
info ref building, plant & equipment
drawings