C - Contract Practice Flashcards
What are the principles of Contract Law?
1) Offer
2) Acceptance
3) Consideration
4) Intent
5) Legality
6) Capacity
What is meant by OFFER?
A promise made by one party which matures into a Contract when accepted by the other party
What is meant by ACCEPTANCE?
Where a party agrees to the terms of the offer presented by another party, creating a binding contract.
- Acceptance must be unconditional
- Negotiations are counter offers, not acceptance
What is meant by CONSIDERATION?
Parties must exchange something of value for a contract to be binding.
- E.g. Selling their house for $1 is valid consideration. Selling for nothing is not.
What is meant by INTENT?
Not all agreements between parties are Contracts. It must be clear the parties intended to enter into a legally binding contract.
What is meant by LEGALITY?
For a contract to be enforceable, the subject matter of the contract cannot be illegal.
- E.g. A contract for the sale of illegal drugs is not enforceable.
What is meant by CAPACITY?
All parties must have the ability to understand the terms of any obligations under the contract.
Consent to the contract must be freely given.
Each party must have the capacity to deliver their consideration (e.g deliver the services and pay for it)
- E.g. Force, fraud, misrepresentation of a party renders a Contract void.
- People under 18, under the influence of drugs or alcohol and those suffering mental health conditions generally lack the capacity to enter into contracts
What is the Construction Contracts Act 2004 (WA)?
CCA
Came into operation 1st January 2005
Often referred to as the ‘Security of Payment Legislation’. Similar legislation exists in each State and Territory around Australia.
What are the objectives of the Construction Contracts Act 2004 (WA)?
1) Prohibits and modifies certain provisions in construction contracts
2) Implies provisions in construction contracts when particular matters are not addressed in the contract
3) Provides a means of rapid adjudication of payment disputes
When does the Construction Contracts Act 2004 (WA) apply?
To all contracts for construction work undertaken in Western Australia.
- Construction work is broadly defined in the Act, it includes most of the commonly understood activities relating to construction.
- Mining and mineral extraction is not covered under the Act
What does the Construction Contracts Act 2004 (WA) PROHIBIT?
1) Pay when paid clauses
2) Contracts which require a payment to be made more than 30 days after the claim is made (previously 50 days)
3) Any terms that attempt to contract our of the operation of the Act.
What are the IMPLIED provisions provided under the Act?
1) When and how to make a payment claim
2) When and how to respond to a payment claim
3) When a payment claim is due to be paid
4) Variations
5) Interest on overdue payments
6) Ownership of goods
7) Duties as to unfixed goods on insolvency
8) Retention money
What does the Act imply regarding when and how to make a payment claim?
The Contractor is entitled to make a claim at anytime, after the Contractor has performed any of its obligation.
What does the Act imply regarding when and how to respond to a payment claim?
The receiving party must provide notice of dispute within 14 days of receiving the claim.
What does the Act imply regarding when a payment claim is due to be paid?
Payment must be made within 28 days after a party receives a claim.
Where they do not reject, or dispute a claim, they must pay the whole amount of the claim, or the amount that is not disputed.
What does the Act imply regarding variations?
The Contractor is not obliged to carry out a variation, unless the Contractor and the Principal have agreed on:
- The nature and extent of the variation
- The amount, or means of which calculating the amount to be paid for the variation
What does the Act imply regarding interest on overdue payments?
Interest is payable if a payment is not made by the time required.
What does the Act imply regarding ownership of goods?
Ownership of the goods pass once the Contractor has been paid, or when the goods are installed.
What does the Act imply regarding duties as to unfixed goods on insolvency?
If the Principal becomes insolvent, they must not allow unfixed goods to become fixtures, or fall into the possession of anyone other than the Contractor.
Secondly, they must allow the Contractor reasonable opportunity to repossess the goods.
What does the Act imply regarding retention money?
Retention money is to be held in trust by the Principal, until the happening of a number of specified events.
The money will be paid to the Contractor, unless the Contractor agrees in writing to give up claim on the money.
What is the rapid adjudication process under the Construction Contract Act?
A quick, cost effective alternative to going to court or arbitration.
- A party intending to take a dispute to adjudication must serve written notes within 90 business days of the dispute arising
- The respondent has 10 business days to respond with supporting documentation
- The adjudicator has 10 business days to make their determination
Under the Act, each of the parties bear their own costs of adjudication.
The decision is binding, although it can be taken into more formal proceedings - e.g. Arbitration, Litigation
What amendments were made to the Construction Contracts Act WA (2004) under the Amendment Bill 2016?
1) Measurement of time changed from ‘days’ to ‘business days’
2) A blackout period was introduced over Christmas and Public Holidays
3) Parties now have 90 business days after the dispute arises to apply for adjudication (previously 28 days)
4) Maximum time allowable for payment of a claim is 30 days (previously 50 days, note this is still measured in days, not business days)
5) Change in the definition of ‘payment claim’, now allows for previously made claims to be recycled.
6) Adjudicators have the power to allow an applicant to withdraw their claim. This enables parties to continue to try to settle their differences, even after lodging the claim for adjudication.
What is a Letter of Intent?
A method of instructing the contractor to proceed with the works before the contract has been formally executed
In what circumstances may a letter of intent be used?
1) Where the employer needs to commence works before a certain date
2) Where there are materials with long lead in times and it would aid the programme
What is the purpose of a letter of intent?
To form a legally binding agreement until the actual contract is signed, that allows work to commence while safeguarding the employers rights
What are the main elements of a letter of intent?
1) The Parties
2) State the Contract it is intended to enter into
3) Contract Sum
4) Clear description of the works
5) State any limits - value / time / scope
6) Procedures - for key issues such as payment / termination / dispute resolution
7) State the ‘Contract will apply retrospectively’
8) Confirm that the Contract created by the LOI will be terminated upon execution of the principle Contract
9) State the basis for calculating payment, should the main contract not be executed
Who issues a letter of intent?
The Client
Who signs a letter of intent?
Both the Client and the Contractor
What are the advantages of a letter of intent?
- Allows the work to commence before the contract is finally agreed
- Provides more safeguards than just telling the Contractor to start without one
What are the disadvantages of a letter of intent?
- May lead to complacency and di-incentivise them to sign the main contract
- Less robust than the main contract
- You would not want the works to continue for very long without getting the Contract signed
What types of letters of intent are there?
1) Comfort Letter
2) Consent to Spend
3) Letters recognising the existence of a binding contract
When may your Client use a Comfort Letter?
A non-binding letter, used to express a party’s intention to act in a particular way at some point in the future
- Such a letter does not oblige the party making the statement to act in that way
- It does not create a Contract between the parties, but may impose certain obligations on parties in relaying to payments for any work undertaken
NOT BINDING
When may your Client use a Consent to Spend Letter?
- Provides an instruction to proceed. This allows works to proceed up to a certain value while the contract is being finalised
- It does create a legally binding contract, which is superseded once the principle contract is executed
BINDING
When may your Client use a Letter Recognising the Existence of a Binding Contract?
- Also referred to as a letter of acceptance
- Used by some forms of Contract to formally execute the Contract itself
- Typically issued only once the Contract has been substantially agreed, usually marks the completion of negotiations between parties
What would you say if the Client asked you to draft a letter of intent?
As it is a legally binding document we are not qualified to draft them as a Quantity Surveyor.
Not covered by PI Insurance
Advise them to seek legal advice
What is a Pre-Construction Services Agreement (PCSA)?
Documents the services that the contractor is to perform before entering into the building contract.
It identifies the terms and conditions under which these services are to be performed.
What is the difference between a letter of intent and a pre-construction services agreement?
- In legal terms, not much between the two
- Key difference is the situations where either is used
- PCSA generally used during a two stage tender, when the Contractor is brought in to liaise with Consultants. Most PCSA’s make no provision for the Contractor to enter site to carry out works.
- Letters of intent usually not part of the tendering process and provide the Contractor to enter site and carry out works
What should be taken into account in the wording of a PCSA?
1) Ensure it does not commit the Client to enter into a building contract
2) Clearly document the services the Contractor is to provide and how they will be paid
3) Ensure they are only obliged to pay for the documented services and nothing else
4) State that the Client may decide at his own discretion whether to appoint the contractor at the end of the second stage, or whether to even proceed with the project at all
5) State that if they do not appoint the Contractor, the Client will not have any liability for any loss of profit, contract or other opportunity.
What are the possible pitfalls of PCSA’s?
- It is possible that PCSA’s may include enabling works although it is not advisable to go beyond that
- The more works the Contractor completes before entering the principle contract (when the Contract Sum and programme are agreed), the weaker the Client’s negotiating position becomes
- If the Contractor is not selected, new Contractor’s will be reluctant to adopt responsibility for previous Contractor’s works - Split liabilities
Would you recommend the use of PCSA’s?
Yes
- Important if the pre-construction period covers a long period of time
- If the contractor is to integrate into the design team and provide advice
- You need to be careful that it does not encourage a lot of work to commence before the building contract is signed
What alternative forms of procurement could be used that may safeguard the Client better than proceeding under a Pre-Construction Services Agreement?
Construction Management
This would allow the Client to start construction before the design is complete as oppose to trying to shoehorn a traditional or D&C contract into a programme where it does not fit
What are the common Contract Documents?
1) Conditions of Contract - and any amendments to the standard forms (General Conditions)
2) Preliminaries
3) Contract Sum Analysis
4) Drawings
5) Specifications
6) Existing Building Information
7) Any Contractors Proposals for Contractors Design Portion
What is a Standard Form of Building Contract?
A form of contract that contains conditions which are applicable, or can be made applicable by the use of alternatives, to a wide range of building projects.
It is common for a standard form of building contract to be used in construction, however, in some cases bespoke contracts will be implemented which will be loosely based on a standard form of Contract.
Name some Standard Forms of Contract
Australian Standard Form (AS)
UK
Joint Contracts Tribunal (JCT)
New Engineering Contract (NEC)
What is a bespoke contract?
Contract conditions that are drafted specifically for a particular project
What are the advantages of Standard Forms of Contract over Bespoke Contracts?
1) Written by legal experts
2) Rights and obligations of each party are clearly set out
3) Risks should have been allocated equitably between the parties
4) Parties should be familiar with the provisions in the form
5) Time and expense of preparing contract documentation is reduced
6) Case law is built up over time - provides a good source of knowledge and clarity of terms
What are the disadvantages of Standard Forms of Contract over Bespoke Contracts?
1) Apportionment of risk is rarely questioned and therefore becomes implicit - not managed appropriately
2) Familiarity is decreased as they are rarely used as printed - regularly amended
3) May not be appropriate to the needs of a particular project or client
4) Using an inappropriate Standard Form for the project will cancel out the advantages
When would a bespoke contract be used rather than a standard form?
- Generally used for major projects with extensive obligations
What are the different types of Standard Form of Contract?
Three types:
- With Quantities
- Without Quantities
- With Approximate Quantities
When would you use a Standard Form of Contract ‘With Quantities’?
- Work has already been designed
- Where there is a Bill of Quantities
- It is a lump sum form of Contract
- Contractor’s risk is limited to price only
- Client takes the risk of errors in the bill
When would you use a Standard Form of Contract ‘Without Quantities’?
- Work has been designed prior to the Contract but there is no bill
- Contract documents include drawings, specification and schedule of rates
- It is a lump sum form of contract
- Contractor’s risk includes both price and quantity
When would you use a Standard Form of Contract ‘With Approximate Quantities’?
- This is a remeasurement form of Contract
- There is no Contract Sum
- Used where the design is not completed at the time of execution
- An approximate Bill of Quantities has been prepared
- Construction is wished to commence prior to the design being completed
What are the main types of Australian Standard Forms of Contract?
AS4000-1997 - General Conditions of Contract
AS4902-2004 - General Conditions of Contract for Design and Construct
AS4905-2000 - Minor Works Contract Conditions
When would you use the AS4000?
Suitable for a wide variety of Construct only projects including building, civil, electrical and mechanical engineering.
- Can be made up with Lump Sum or Schedule of Rates, or both
- Has provision for a Bill of Quantities
- Requires administration by a Principal-appointed Superintendent
When would you use the AS4902?
Suitable for Design and Construct Projects
When would you use the AS4905?
Suitable for construction projects of a simple nature and limited monetary value (Advisable under $250,000)
What is a Measured Term Contract?
Where a client requires maintenance / minor works to be undertaken on a regular basis, over a defined period of time, on a defined list of properties
Contract agreed on a Schedule of Rates for carrying out certain types of work
Can be let on a fixed, or fluctuating price basis
Contains a break provision for terminating the Contract early
What is the legal principle of Contra Proferentum?
Where ambiguous clauses are construed against the party who put the Contract forward.
If a Contract is prepared by one party who may use superior bargaining power to get the other party to accept it, Contra Proferentem may apply
It does not apply to standard forms of Contract, although it would apply to any amendments
It applied to bespoke contracts
Can a Quantity Surveyor provide legal advice for Contracts?
NO
Quantity Surveyor’s are not insured, not qualified to give legal advice
What is retention?
A sum that is generally deducted at each monthly payment claim.
What is the purpose of retention?
It provides the client with some security that the Contractor will return to correct any defect during the defects liability period.
If the Contractor does not return, the client can use the retention held to fund the payment of others to correct the defects.
What are the typical features of retention?
1) It is usually a fixed % of the Contract Sum (typically 5%)
2) 50% is typically released at Practical Completion
3) Remaining 50% is released at the end of the defects liability period
What are the disadvantages of retention?
Can cause cash flow problems for contractors, especially if the retained amount is significant
What alternatives are there to retention?
Retention Bonds e.g. Bank Guarantees
What principles apply to using Retention Bonds?
1) Provided by the contractor in lieu of retention from interim payments
2) Should be the same value as the retention would have been
3) The alternative needs to be stated within the Contract particulars
4) Eases cash flow problems for Contractors
5) Same principles of amount and periodic release apply
What are the disadvantages of the use of retention bonds?
1) Employer pays a premium for taking out the bond
2) Increases the employers cash flow
3) The employer does not get the interest accruing on the retention held
4) It may reduce the Contractors incentive to complete the defects
How is retention / retention bonds applied on Construction Management Contracts?
- Retention is applied to each individual trade contract
- Practical completion certificates must be issued for each trade package, so there are numerous defects liability periods.
- This means retention must be released when required for each individual contract
When does retention get released?
50% at Practical Completion
50% at the end of the defects liability period
Who keeps the interest on retention money?
The Client
What is Assignment?
Where the RIGHTS AND BENEFITS of one contractual party are transferred to a third party
Assignment allows the benefits of a contract to be transferred, but not the burden (burdens must be novated).
The right to assign does not need to be agreed as part of the contract. However, it can be restricted or excluded from the contract
Can benefits be assinged under the contracts you work with?
Amended AS4000 - Typically excluded from contracts i have used.
Clause 9.1 - Parties must obtain prior written approval to assign under the contract, cannot be unreasonably withheld.
Can you provide an example of when assignment may occur?
A contractor can assign the benefit of payment to a sister company to improve cash flow.
However, assignment cannot transfer the responsibility to undertake the WUC
What is Novation?
Where Contractual RIGHTS AND OBLIGATIONS are transferred to a third party
Benefits and burdens can be transferred under novation.
Novation agreement is not possible without consent.
Can you provide an example of when novation may occur?
Common in D&C contracts where the design team is appointed by the Client, once the contractor is appointed, the design team are novated to work for the Contractor.
Contractor is not automatically responsible for the design prior to novation, to achieve this the contract needs to state the contractor has examined and adopted the design
What affect does novation have on the client’s rights?
- Lose all contractual relations with the novated party
- Common for there to be a collateral warranty