Bunkering Flashcards
1
Q
Pre Bunker Checklist
A
- State of adjacent waters noticed.
- Vessel properly secured to dock.
- Check suppliers product corresponds to ordered product (specified sheet).
- Agree quantity to be supplied.
- Check valves are open.
- Day tanks full and supply valves closed.
- Warnings signs in position eg. No Smoking
- SOPEP plan available.
- Clean up material in place.
- Oil Boom in place.
- Foam fire extinguisher placed at bunker station.
- Fuel tank supply valves open.
- Agree stop/start signals between vessel and barge/road tanker.
- Bravo flag flying/red light showing.
- Agree pumping/transfer rate.
- Agree emergency shut down procedure.
- Check hose and couplings are secure and in good order.
- Fuel nozzle and hosed secured to vessel.
- Check gauges on barge/road tanker/vessel and note readings.
- Bunker valve open.
- Unused manifold connections blanked off.
- Master informed.
- Signal pumping to commence.
2
Q
State the immediate action that must be taken in the event of a spill of bunkers.
A
- Stop the bunkering operation.
- Raise the alarm.
- Inform the Master and Engine Room.
- Inform port authorities and barge.
- Fix the problem.
- Mop up/clean up the area.
- Dispose the waste and make sure you get the receipt.
Use SOPEP equipment.
3
Q
State the document in which the spill should be recorded.
A
Oil Record Book Part 1