Budget & Resources Flashcards

1
Q

According to the Process Groups model, what are the processes of cost management?

A

Plan Cost Management
Estimate Costs
Determine Budget
Control Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What combined baselines are called the performance measurement baseline?

A

Scope, schedule, and cost baselines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is earned value analysis, and how is it used?

A

It is an analysis method that uses earned value and other metrics to evaluate how well the project is doing relative to what was planned to date

Together with other measures the project manager can determine the overall project performance against the performance measurement baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is earned value management (EVM)?

A

The practice of managing scope, schedule, and cost using earned value analysis to control the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What artifact results from the Plan Cost Management process?

A

Cost management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What artifacts are needed for the Estimate Costs process?

A

Resource requirements documentation
Cost and quality management plans
Scope and schedule baselines
Lessons learned and risk registers
Policies and historical records related to estimating
Templates and processes including those from past projects
Corporate governance
Marketplace conditions, commercial cost databases, exchange rates, inflation, and supply sources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do variable costs differ from fixed costs?

A

Variable costs change with the amount of production or amount of work done on the project

Fixed costs do not change as production changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a direct cost?

What is an indirect cost?

A

Direct cost: A cost that is directly attributable to the work on the project

Indirect cost: Overhead costs or costs incurred for the benefit of more than one project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Name the advantages of analogous estimating.

A

Quick

Activities do not need to be identified

Less costly to create

Provides cost constraints to evaluate high-level project feasibility

Overall project costs will be capped

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Name the advantages of bottom-up estimating.

A

More accurate

Gains buy-in from the team

Based on a detailed project and deliverable analyses

Provides a basis for monitoring and controlling, performance
measurement, and management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Name the typical range for the following:

rough order of magnitude (ROM) estimate
budget estimate
definitive estimate

A

ROM estimate: –25 to +75 percent from actual

Budget estimate:–10 percent to +25 percent from actual

Definitive estimate:+/–10 percent from actual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What key artifacts result from the Estimate Costs process?

A

Cost estimates
Basis of estimates
Updates to project documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What methods are used to estimate costs in an adaptive environment?

A

T-shirt sizing
Affinity estimating
Planning Poker®

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is cost aggregation?

A

Pulling together the costs of all activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

At what point are contingency reserves added to the budget?

A

After risk management planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the difference between a cost budget and a cost baseline?

A

The cost baseline is an estimated total cost performance measurement baseline; it does not include the management reserves

The cost budget is the total that includes the cost baseline + management reserves

17
Q

What agile tool can be used to anticipate future budgetary issues on agile projects?

A

Velocity

18
Q

On adaptive projects the majority of cost estimates for projections and estimate at completion are based on what?

A

Burn rates

19
Q

What key artifacts result from the Determine Budget process?

A

Cost baseline
Project funding requirements
Updates to project documents

20
Q

How can progress reporting help the project manager?

A

It can help control schedule and costs

It can help the project manager assess whether the project is on track through earned value analysis

21
Q

What is the purpose of reserve analysis?

A

It allows the project manager to identify and apply lessons learned in controlling costs

Cost control includes analyzing where contingency reserves are still necessary or where new reserves are required

22
Q

What is the difference between planned value and earned value?

A

Planned value is the estimated value of the work planned, as of today

Earned value is the estimated value of the work actually accomplished, as of today

23
Q

What is actual cost

What is budget at completion?

A

The actual cost incurred for the work accomplished, as of today

The project’s planned budget; indicates what the end cost of the project would be if everything went according to plan

24
Q

What is the formula for cost variance?

A

EV − AC = CV

25
Q

What is the formula for schedule variance?

A

EV – PV = SV

26
Q

What is the formula for cost performance index?

A

EV
—— = CPI
AC

27
Q

What is the formula for schedule performance index?

A

EV
—— = SPI
PV

28
Q

What does a positive number indicate for CV or SV?

A

A positive number indicates that the project is under budget (CV) or ahead of schedule (SV)

A negative number would indicate that the project is over budget (CV) or behind schedule (SV)

29
Q

What does a number less than one indicate with SPI and CPI?

A

Greater than one is good

Less than one is bad