Budget & Resources Flashcards
According to the Process Groups model, what are the processes of cost management?
Plan Cost Management
Estimate Costs
Determine Budget
Control Costs
What combined baselines are called the performance measurement baseline?
Scope, schedule, and cost baselines
What is earned value analysis, and how is it used?
It is an analysis method that uses earned value and other metrics to evaluate how well the project is doing relative to what was planned to date
Together with other measures the project manager can determine the overall project performance against the performance measurement baseline
What is earned value management (EVM)?
The practice of managing scope, schedule, and cost using earned value analysis to control the project
What artifact results from the Plan Cost Management process?
Cost management plan
What artifacts are needed for the Estimate Costs process?
Resource requirements documentation
Cost and quality management plans
Scope and schedule baselines
Lessons learned and risk registers
Policies and historical records related to estimating
Templates and processes including those from past projects
Corporate governance
Marketplace conditions, commercial cost databases, exchange rates, inflation, and supply sources
How do variable costs differ from fixed costs?
Variable costs change with the amount of production or amount of work done on the project
Fixed costs do not change as production changes
What is a direct cost?
What is an indirect cost?
Direct cost: A cost that is directly attributable to the work on the project
Indirect cost: Overhead costs or costs incurred for the benefit of more than one project
Name the advantages of analogous estimating.
Quick
Activities do not need to be identified
Less costly to create
Provides cost constraints to evaluate high-level project feasibility
Overall project costs will be capped
Name the advantages of bottom-up estimating.
More accurate
Gains buy-in from the team
Based on a detailed project and deliverable analyses
Provides a basis for monitoring and controlling, performance
measurement, and management
Name the typical range for the following:
rough order of magnitude (ROM) estimate
budget estimate
definitive estimate
ROM estimate: –25 to +75 percent from actual
Budget estimate:–10 percent to +25 percent from actual
Definitive estimate:+/–10 percent from actual
What key artifacts result from the Estimate Costs process?
Cost estimates
Basis of estimates
Updates to project documents
What methods are used to estimate costs in an adaptive environment?
T-shirt sizing
Affinity estimating
Planning Poker®
What is cost aggregation?
Pulling together the costs of all activities
At what point are contingency reserves added to the budget?
After risk management planning