Brain Dump Formulas Flashcards
[n*(n – 1)] / 2
(# of) Communication Channels Equation
n = number of stakeholders on the team, incl the project manager.
(Optimistic + Most Likely + Pessimistic) / 3
Three-Point Estimation Formula (aka Triangular Distribution)
Use for Scheduling and Cost Estimates
Optimistic = What is the best-case that will occur?
– Most Likely = Realistically speaking, how long would it take/how much would it cost?
– Pessimistic = What is the worst-case estimate that would occur?
(Optimistic + 4*Most Likely + Pessimistic ) / 6
PERT Estimation Formula (“Beta Distribution”)
Use for Scheduling and Cost Estimates
Optimistic = What is the best-case that will occur?
– Most Likely = Realistically speaking, how long would it take/how much would it cost?
– Pessimistic = What is the worst-case estimate that would occur?
LS – ES or LF – EF
Critical Path Analysis Formulas
If Float = 0, then the activity is on the critical path
If Float < 0, then the activity is Behind Schedule!
– LS = Late Start = Latest time that a task can start, without delaying its Late Finish
– ES = Early Start = Earliest time that a task can start
– LF = Late Finish = Latest time that a task can be completed, without affecting a Successor Activity
– EF = Early Finish = Earliest time that a task can finish
just think that a negative float is bad (bad for being behind schedule).
EV – PV
Earned Value Analysis (EVA):
Schedule Variance, SV
– EV = Earned Value = The ACTUAL value for the work which has been “earned” or completed thus far.
– PV = Planned Value = The “planned” approved budget for completing the scheduled work
SV < 0 means… Behind Schedule (BAD)
SV = 0 means… On Schedule (NEUTRAL)
SV > 0 means… Ahead of Schedule (GOOD)
EV – AC
Earned Value Analysis (EVA):
Cost Variance, CV
– EV = Earned Value = The ACTUAL value for the work which has been “earned” or completed thus far.
– AC = Actual Cost = How much was actually spent to perform the work?
CV < 0 means… Over Budget (BAD)
CV = 0 means… On Budget (NEUTRAL)
CV > 0 means… Within Budget (GOOD)
BAC – EAC
Earned Value Analysis (EVA):
Variance At Completion, VAC
Budget at Completion (BAC) is a measure that is often used in earned value management to track the actual cost of a project against its forecasted budget.
Equivalent annual cost (EAC)
EV / PV
Index Equations: SPI
SCHEDULE PERFORMANCE INDEX = EARNED VALUE / PLANNED VALUE
SPI < 1 means… Behind Schedule (BAD)
SPI = 1 means… On Schedule (NEUTRAL)
SPI > 1 means… Ahead of Schedule (GOOD)
EV / AC
COST PERFORMANCE INDEX= (EARNED VALUE / ACTUAL COST)
CPI < 1 means… Over Budget (BAD)
CPI = 1 means… On Budget (NEUTRAL)
CPI > 1 means… Within Budget (GOOD)
(BAC – EV) / (EAC? – AC)
To-Complete-Performance Index, TCPI
(BUDGET AT COMPLETION - EARNED VALUE) / EASTIMATE AT COMPLETION - ACTUAL COST)
When to use? Measuring the cost efficiency in order to complete the project per the plan
**Note: In the above two equations for TCPI, BAC is replaced with EAC in the denominator of the equation.