Block 2 - Commission Furnaces & Ovens - Commission Draft Control Systems Self Assessment Flashcards

1
Q

What is the main goal of conducting system response tests?

A

To ensure the draft control system responds correctly to changes in operating conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why is documentation of compliance with B149.1 code clauses necessary?

A

To verify that all materials, dimensions, and installation practices comply with the code’s requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of calibrating instruments in the draft control system?

A

To ensure accurate readings and reliable data for monitoring and control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why is interlock functionality important in a draft control system?

A

To ensure safe operation by activating under the correct conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why is system integration with boiler control and other relevant equipment crucial?

A

To ensure synchronized operation and overall system stability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why is it important to verify all necessary permits during the commissioning process?

A

To ensure legal operation and adherence to safety standards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What code clauses should be consulted for non-engineered sizing of the draft control system?

A

B149.1 code clauses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the main purpose of commissioning draft control systems for gas-fired industrial appliances?

A

To regulate air flow and maintain proper combustion conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What should be inspected for loose connections, damaged wiring, and potential issues?

A

Electrical connections

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What should be verified during the correct installation of the draft control system?

A

Compliance with relevant industry standards and manufacturer guidelines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why is it necessary to balance airflow in the exhaust system?

A

To ensure uniform distribution and proper ventilation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What should be documented and reported during the commissioning process?

A

Data logs, calibration records, and changes to initial settings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is included in the inspection of oven components?

A

Inspecting burners, ignition systems, controls, sensors, and safety devices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

During performance validation, which parameter is measured to ensure optimal operation?

A

External static pressure and temperature rise

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

During gas system checks, what method can be used to detect gas leaks?

A

Soap solution or pressure decay test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the purpose of performing a combustion analysis during pilot and main burner testing?

A

To verify that the combustion system operates within the specified air-fuel ratio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the purpose of reviewing the oven design and documentation during pre-commissioning checks?

A

To ensure all aspects of the setup align with the original design intent

17
Q

What should be verified during ventilation and exhaust system checks?

A

Correct installation and no obstructions in the airflow path

18
Q

Why is it essential to test the pilot burner?

A

To ensure proper ignition and flame stability

19
Q

Which of the following systems requires TSBC design registration even if CSA approved?

A

DFMA (Direct-Fired Makeup Air) Systems

20
Q

Which of the following is a critical aspect of inspecting exhaust fans?

A

Verifying proper installation and functioning

21
Q

What should be documented and reported during the commissioning process?

A

All inspections, tests, and adjustments made

22
Q

What is the objective of the ignition system test?

A

To verify reliable and safe ignition of the gas

23
Q

What is the purpose of leak testing in the fuel system checks?

A

To detect any leaks and prevent hazardous conditions

24
Q

What is one of the key steps in the calibration of instruments?

A

Ensuring accurate readings from temperature, pressure, and airflow sensors

25
Q

What is the first step in the pre-commissioning checks for an industrial furnace?

A

Reviewing design and documentation

26
Q

What is the importance of ensuring proper ventilation in the ducting system for furnaces and ovens?

A

To maintain optimal indoor air quality

27
Q

Why is it important to check the temperature control system?

A

To ensure accurate setpoints and stable temperature control

28
Q

Which of the following should be confirmed during permit and approval verification?

A

Installation permits and product approval permits are in place

29
Q

What must field-designed systems go through before proceeding with the TSBC registration?

A

Engineering design stamped by a certified engineer

30
Q

What should be done if air is present in the fuel lines during fuel system checks?

A

Purge air from the fuel lines

31
Q

Which of the following is checked during the safety system verification?

A

Emergency shut-offs, alarms, and interlocks

32
Q

What should be included in the comprehensive documentation of the start-up process?

A

Data logs, calibration records, and changes to initial settings

33
Q

What does the start-up sequence verification involve?

A

Ensuring each step follows the manufacturer’s guidelines

34
Q

What is one of the key steps in verifying control systems?

A

Testing them to ensure they respond appropriately to changes

35
Q

Why is it essential to calibrate sensors used in the exhaust system?

A

To ensure accurate readings and reliable operation

36
Q

Which system ensures the furnace has a reliable and safe ignition of the fuel?

A

Ignition system

37
Q

What is the objective of the temperature control system verification?

A

To ensure sensors are correctly positioned and calibrated

38
Q

What is the primary goal of engineering design approval for furnace and oven systems?

A

To guarantee engineering design is approved by recognized standards organizations

39
Q

During the ductwork inspection, what should be checked to avoid compromising the system’s performance?

A

Damage, leaks, or improper connections