Block 2 - Appliance Startup Procedures - Commission Flame Safeguard Systems Flashcards
What are the regulatory requirements for gas appliances?
Obtain necessary permits, secure product approval, complete field inspections.
Failure to adhere could have serious consequences for your career as an Industrial Gasfitter.
How does Technical Safety BC evaluate applications for product approvals?
On a case-by-case basis, requiring certification by a recognized body if a Canadian-recognized standard or other recognized document exists.
What is the first step for non-certified appliances lacking Canadian certification?
Apply to register the uncertified gas appliance (Gas Design Registration).
What must be obtained after receiving a journal number for a design?
Product Approval permit.
What is required after completing each phase of the gas system authorized by the permit?
Request an inspection.
What must be done during commissioning of a gas appliance?
A Safety Officer will field certify the unit and affix a decal.
What does the complete Product Approval include?
Commissioning permission.
What does section 31 of the Gas Safety Regulations state?
A person must not install an appliance unless it displays a certification mark or an approval mark.
What are potential penalties for performing regulated work without a permit?
Fines up to $100,000 and/or imprisonment for up to 18 months for individuals; fines up to $200,000 for corporations.
What appliances require mandatory commissioning approval under section 26 (2) of the Gas Safety Regulations?
Direct-fired non-recirculating make-up heater, conversion burners, direct-fired equipment, forced draft appliances over 409,600 Btuh.
How much notice must the permit holder give before requesting an assessment?
At least 48 hours prior to expected commissioning time.
Who witnesses the testing and commissioning of the appliance?
The safety officer.
What should be done if the commissioning approval assessment is waived?
Submit a Start Up report to the safety officer.
What should be initiated early in the commissioning process?
Communication between the gas fitter of record and the Gas Safety Officer.
What must gas fitters submit to Technical Safety BC after a start-up?
A detailed appliance start-up report.
What should the start-up gas fitter information match?
The gas fitter of record on the permit application.
What is required for the setup and training of the operator?
Manuals and wiring diagrams.
What should be checked during a pre-start-up inspection?
Function of gaskets, removal of packing, compliance of valve train, and system connections.
What are some items to check during commissioning?
- Function of gaskets
- Valve train compliance
- System connections
- Electrical terminations
- Belt and pulley alignment.
What must be confirmed regarding wiring before start-up?
Wiring is complete and as per drawings.
What must be checked regarding motor rotation?
Correct rotation of 3-phase motors.
How can the rotation of a 3-phase motor be changed?
Interchanging any two of the three lines feeding the motor.
What must be done to ensure safety during the commissioning process?
Perform a Job Hazard Assessment.
What is the importance of checking every single wiring termination?
To prevent system failures due to loose connections.
True or False: Personal locks may be accepted on all industrial sites.
False.
Fill in the blank: A complete Product Approval includes _______.
[commissioning permission].
What is the primary hazard associated with flame safeguards?
Fire or Explosion Hazard. Can cause property damage, severe injury or death.
What must be done before starting tests on flame safeguards?
Close all manual fuel shutoff valve(s).
What should be confirmed regarding the flame safeguard model?
Confirm that the model is correct and meets all code requirements for the application.
What is necessary regarding grounding when installing a flame safeguard?
Confirm that there is a connected dedicated ground wire installed on the subbase.
What should be checked for tightness during installation?
Check the tightness of every wiring terminal.
What is the purpose of performing a static checkout?
Verify that the subbase is wired correctly, and the external controllers, limits, interlocks, actuators, valves, transformers, motors, and other devices are operating properly.
What is required to complete some of the tests during the static checkout?
Gas pressure to the low gas pressure switch, or it needs to be jumped out.
What tools are needed for performing the static checkout?
A multi-meter and a pair of 14 AWG jumpers with alligator clips at each end.
Fill in the blank: To perform the Static Checkout, you will need a _______.
[multi-meter]
What should be done before opening the main disconnect when adding or removing jumpers?
Open the master switch.
What is the first test conducted during the static checkout?
Check supply power.
What voltage should be checked between terminals 5 (L1) and L2?
Supply power voltage.
What is the second test during the static checkout?
Check Limit Circuit.
What should be checked if the voltage reading is abnormal?
Check the limit circuit components.
What is the purpose of the lockout interlocks test?
Ensure the system locks out correctly when conditions are not met.
What should be observed during the ignition transformer test?
You should hear the buzz of the ignition spark.
What should be heard when checking the pilot valve?
You should hear the click of the opening of the pilot solenoid valve.
What is tested in tests #6 and #7 during the static checkout?
Check Safety Shutoff Valves (SSOV’s).
What should be observed when the main gas valves are opened?
Observe the opening of the main gas valves.