ARE Review Manual Flashcards
Project Manual Contents
Bidding Documents Supplements to Bid Forms Contract Forms General and Supplementary Conditions Technical Specifications
Proprietary Specs
Closed Spec - Call out specific manufacturer, most control
Base-Bid with Alternates Specs
Closed Spec - Proprietary Product but allows substitutions
Descriptive Spec
Open Spec - Written requirements for material or product
Prescriptive Spec
Closed - specific brand names or material
Performance Spec
Open - specifies the final result
Reference Standard Spec
Uses a material, product or process to set a standard by an accepted authority or test method. EX( UL Listed)
Pure Performance Spec
Specifies the requirements of the finish product, but allows contractor to take full control over selecting a product that could match. creating an opportunity for achieving the end result
Agency
Three Parties:
Principle - Owner
Agent - Architect (on behalf of owner)
3rd Party - Contractor
Design-Award-Build (Design-Bid-Build) is considered what type of project delivery?
Traditional project delivery
What is a Fast-Track Project Approach
Overlaps part of design with construction to reduce total overall time. May have a Construction Manager, Either independent or dependent of GC
What is Design-Build Project Approach
Owner contracts with one entity for design and construction services (Different structures for the one entity)
Compensation Methods (architect)
Stipulated Sum (Fixed Fee) Cost plus Fee Percentage of construction costs Unit Cost (EX. Square Footage or Per Apartment)
Compensation Methods (GC)
Fixed Fee
GMP
Cost plus Fee
Unit Cost
Change Order
Written agreement that changes the original contract and affects costs and time
Change directive
Directs contractor to proceed even if contractor does not agree with basis for adjustment to contract sum or time. The actual change of cost and time is determined by submittals and reviewed by the architect and submitted as a change order.
Mechanic’s Lien
Claim from one party against property of another party to satisfy a debt.
Addenda (Addendum)
Written or graphic document issued by architect prior to execution of the contract that modifies or interprets the bidding document.
Submittals
Include: shop drawings sample product data Calculations
Shop Drawings
Drawings, Diagrams, Schedules and other data to show how a sub or supplier proposes to supply and install work to conform to the contract documents
Sample
Physical example of portion of work, used as standards of appearance and workmanship for final judgement
Product Data
Information that illustrates portion of the work
Intermediate Payment
GC to submit to architect a periodic payment that the architect will determine if it meets the value in the field. Retainer typically withheld
Final Payment
After final inspection by the architect, when work is complete and acceptable under conditions of the contract, it is issued.
Project Closeout
It is when building work is completed, the structure is made ready for occupancy and all remaining documentation takes place
Business Organization Types
Sole Proprietorship Partnerships Corporations LLC/LLP (Limited Liability) Joint Ventures
Office Organization
Departmental
Studio - Collaborative setting
Duties
What one person “owes” another per a working relationship, including a contract
Liability
Legal responsibility for injury or damage to another person or property
Negligence
Failure to use due care to avoid harming another person or property