AMA Q22 - Chapter 8 Flashcards

1
Q

List the 7 types of operational causes of variances

A
  • Material price
  • Material usage
  • Labour rate
  • Idle time
  • Labour efficiency
  • Fixed overhead expenditure
  • Fixed overhead volume
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Interdependence of variances

A

how one change in a variance can have a direct impact on another

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Three categories of variances

A
  1. Controllable expenditure- poor purchase decisions
  2. Uncontrollable expenditure - market changes causing fluctuations in price
  3. Inaccurate standard - poor planning + use of unrealistic standard
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How is non-controllable variance calculated?

A

comparing the original standard to the revised one

revised

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How is controllable variance calculated?

A

Comparing the revised standard to the actual cost

actual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly