AIA G Series Flashcards

1
Q

What is the AIA G701?

A

Change Order Form

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the AIA G702?

A

Pay Application

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the AIA G703?

A

Instructions to for Pay AP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the AIA G704?

A

Certificate of Substantial Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Change Order

A

A change to the scope of work that is detailed in writing to the owner and contractor for approval.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Construction Change Directive

A

A direction given to the contractor without need for owner approval.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What details are included in G701? (8)

A
  1. Description of change
  2. Original contract sum
  3. Net change of all previous change orders
  4. Current contract sum at the time of change order
  5. Change in contract sum proposed for the change order
  6. New contract sum after execution of change order
  7. Contract time adjustments per the change order
  8. New date of substantial completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Who must sign the G701?

A

Architect, Owner, and Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does the subcontractor certify in the G702?

A

That the work noted within has been completed in accordance with contract docs AND that the contractor has paid them for all previous certificates of payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What constitutes a retainage on the G702?

A

5% of the completed work to-date and a set percentage of presently stored materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who must sign the G702?

A

Subcontractor and Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the chain of distribution for the G702?

A

Subcontractor > Contractor > Architect > Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who establishes the date of substantial completion on form G704?

A

The architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is listed within form G704?

A
  1. Date of substantial completion
  2. Warranties that do not commence on date of SC (indicate start dates)
  3. Work to be completed or corrected
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Who must sign the G704?

A

Architect, Owner, and Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly