AHPP Chapter 15 - Project Definition Flashcards
1
Q
What are the three main categories of architectural services?
A
Pre-design services
Design-through-construction services
Post-construction services
2
Q
What is the AIA document number for Digital Data Protocol Exhibit?
A
E201
Regards the transmission or exchange of digital data
3
Q
What is the AIA document number for BIM Protocol Exhibit?
A
E202
4
Q
What are the four AIA document versions that relate to the size of a project?
A
B101 -
B102 -
B103 -
B104 -
5
Q
What are some ways that a firm can be valued?
A
- Design preeminence
- Project expertise
- Quality of service
- Project management/leadership
- Unique services
- In-depth understanding
6
Q
What is a risk of Fast-track projects, for architects?
A
- Issuing documents take more effort early on, discrepancies will happen
7
Q
When should a Stipulated Sum fee be used?
A
- When the scope of the work is understood
The architect can finish faster for a higher profit