7 Project Cost Management Flashcards

1
Q

The actual amount of monies the project

has spent to date.

A

Actual cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

An approach that relies on historical
information to predict the cost of the
current project. It is also known as topdown estimating and is the least reliable
of all the cost-estimating approaches.

A

Analogous estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

An estimating approach that starts from
zero, accounts for each component of the
WBS, and arrives at a sum for the
project. It is completed with the project
team and can be one of the most timeconsuming and most reliable methods to
predict project costs.

A

Bottom-up estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
This estimate is also somewhat broad
and is used early in the planning
processes and also in top-down
estimates. The range of variance for the
estimate can be from –10 percent to +25
percent.
A

Budget estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A cost-estimating approach that uses a
database, typically software-driven, to
create the cost estimate for a project.

A

Commercial database

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

An allowance to account for
overruns in costs. They’re used at the project
manager’s discretion and with
management’s approval to counteract
cost overruns for scheduled activities and
risk events.

A

Contingency reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
Costs are parallel to each WBS work
package. The costs of each work
package are added to their
corresponding control accounts. Each
control account then is added to the
sum of the project costs.
A

Cost aggregation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A time-lapse exposure of when the
project monies are to be spent in relation
to cumulative values of the work
completed in the project.

A

Cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
The cost aggregation achieved by
assigning specific dollar amounts for
each of the scheduled activities or, more
likely, for each of the work packages in
the WBS. It applies the cost
estimates over time.
A

Cost budgeting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
A system that examines any changes
associated with scope changes, the cost
of materials, and the cost of any other
resources, and the associated impact on
the overall project cost.
A

Cost change control system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

It dictates how cost variances will be managed.

A

Cost management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The monies spent to recover from not
adhering to the expected level of quality.
Examples may include rework, defect
repair, loss of life or limb because safety
precautions were not taken, loss of sales,
and loss of customers. This is also known
as the cost of nonconformance to quality.

A

Cost of poor quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The monies spent to attain the expected
level of quality within a project. Examples
include training, testing, and safety
precautions.

A

Cost of quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Measures the project based on its

financial performance. The formula is EV/AC.

A

Cost performance index (CPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The difference of the earned value
amount and the cumulative actual costs
of the project. The formula is EV – AC.

A

Cost variance (CV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
This estimate type is one of the most
accurate. It’s used late in the planning
processes and is associated with bottomup estimating. You need the WBS in
order to create the definitive estimate.
The range of variance for the estimate
can be from –5 percent to +10 percent.
A

Definitive estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Costs are attributed to the project
work and cannot be shared among
projects (for example, airfare, hotels,
long-distance phone charges, and so on).

A

Direct costs

18
Q
It´s the physical work
completed to date and the authorized
budget for that work. It is the percentage
of the BAC that represents the actual
work completed in the project.
A

Earned value (EV)

19
Q

These forecasting formulas predict the
likely completed costs of the project
based on current scenarios within the
project.

A

Estimate at completion (EAC)

20
Q
An earned value management formula
that predicts how much funding the
project will require to be completed.
Three variations of this formula are based
on conditions the project may be
experiencing.
A

Estimate to complete (ETC)

21
Q
Costs that remain constant throughout
the life of the project (the cost of a piece
of rented equipment for the project, the
cost of a consultant brought on to the
project, and so on).
A

Fixed costs

22
Q

An organization’s approach to managing
cash flow against the project deliverables
based on a schedule, milestone
accomplishment, or data constraints.

A

Funding limit reconciliation

23
Q
Costs that are representative of more
than one project (for example, utilities for
the performing organization, access to a
training room, project management
software license, and so on).
A

Indirect costs

24
Q

An event that will likely happen within the
project, but when it will happen and to
what degree is unknown. These events,
such as delays, are usually risk-related.

A

Known unknown

25
Q

An approach that assumes the cost per
unit decreases the more units workers
complete, because workers learn as they
complete the required work.

A

Learning curve

26
Q

A market condition where the market is
so tight that the actions of one vendor
affect the actions of all the others.

A

Oligopoly

27
Q

The total cost of the opportunity that is
refused to realize an opposing
opportunity.

A

Opportunity cost

28
Q
An approach using a model to
extrapolate what costs will be needed for
a project (for example, cost per hour and
cost per unit). It can include variables and
points based on conditions.
A

Parametric estimating

29
Q
It's the work scheduled and
the budget authorized to accomplish that
work. It is the percentage of the BAC that
reflects where the project should be at
this point in time.
A

Planned value (PV)

30
Q

The final variance, which is discovered
only at the project’s completion. The
formula is BAC – AC.

A

Project variance

31
Q
This is a statistical approach to predicting
what future values may be, based on
historical values. It creates 
quantitative predictions based on
variables within one value to predict
variables in another. This form of
estimating relies solely on pure statistical
math to reveal relationships between
variables and to predict future values.
A

Regression analysis

32
Q
Cost reserves are for unknown unknowns
within a project. The management
reserve is not part of the project cost
baseline, but is included as part of the
project budget.
A

Reserve analysis

33
Q
This rough estimate is used during the
initiating processes and in top-down
estimates. The range of variance for the
estimate can be from –25 percent to +75
percent.
A

Rough order of magnitude

34
Q

Measures the project based on its
schedule performance. The formula is
EV/PV.

A

Schedule performance index (SPI)

35
Q

The difference between the earned value
and the planned value. The formulas is
EV – PV.

A

Schedule variance (SV)

36
Q

Many vendors can provide what your
project needs to purchase, but you prefer
to work with a specific vendor.

A

Single source

37
Q

Only one vendor can provide what your
project needs to purchase. Examples
include a specific consultant, specialized
service, or unique type of material.

A

Sole source

38
Q

Monies that have already been invested

in a project.

A

Sunk costs

39
Q

A formula to forecast the likelihood of a
project to achieve its goals based on
what’s happening in the project right now.
There are two different depending on what you want to
accomplish. If you want to see if your
project can meet the budget at
completion, you’ll use this formula: (BAC – EV)/(BAC – AC). If you want to
see if your project can meet the newly
created estimate at completion, you’ll use
this version of the formula: (BAC
– EV)/(EAC – AC).

A

To-Complete Performance Index TCPI

40
Q
Costs that change based on the
conditions applied in the project (the
number of meeting participants, the
supply of and demand for materials, and
so on).
A

Variable costs

41
Q

The difference between what was

expected and what was experienced.

A

Variance

42
Q

A forecasting formula that predicts how
much of a variance the project will likely
have based on current conditions within
the project. The formula is BAC – EAC.

A

Variance at completion (VAC)