6 | Planning Project Costs Flashcards
In this lesson, you will: • Estimate project costs. • Estimate the cost baseline. • Reconcile funding and costs.
What are the 6 common cost estimate types?
1. Rough Order of Magnitude (ROM) estimate 2. Range of estimate 3. Approximate estimate 4. Budgetary estimate 5. Definitive (or control or detailed ) estimate 6. Phased (or rolling wave or moving window) estimate
Rough Order of
Magnitude (ROM)
estimate?
Developed without any detailed base data and often based on high level historical data, expert judgment, or a costing model. ROM is generally made early in the project.
Accuracy: -25 percent to +75 percent
Range of estimate?
Often used as an alternative to ROM where the accuracy of the estimate is not well known. So, rather than $10M ±30 percent, the estimate can be stated as $7M to $13M.
Accuracy: ±35 percent
Approximate estimate?
Based on more information than ROM estimates, but still lacks the detail required for high accuracy. Approximate estimate may be possible if the project is similar to previous ones with reliable historical data for costing or where a proven costing model is applicable.
Accuracy: ±15 percent
Budgetary estimate?
Often used for appropriation purposes.
Accuracy: -10 percent to +25 percent
Definitive (or control or
detailed ) estimate?
Based on detailed information about project work. Definitive estimate is developed by estimating the cost for each work package in the WBS.
Accuracy: -5 percent to +10 percent
Phased (or rolling wave or
moving window) estimate?
Allows the use of ROM or approximate estimates for later parts of work, while work that must be done earlier in the project life cycle is estimated at the definitive level.
Accuracy: ±5 percent to ±15 percent in the window closest to present time; ±35 percent farther in the future
Project Management Estimating Software?
Project management estimating software is any software application that assists in cost estimating while managing projects. This helps simplify the usage of cost estimating techniques and facilitates effective cost estimate alternatives.
Vendor Bid Analysis?
Is a cost estimation technique based on the bids obtained from vendors. The proposed costing from vendors is considered while developing estimates for the project. Generally, a part of the project is outsourced to a vendor, so the costing for that outsourced part of the project can be sought from the vendors through their proposals, bids, or quotations. The costing can be indicative figures with less accuracy or very accurate detailed figures.
Activity Cost Estimates?
Activity cost estimates provide estimates of costs necessary to finish project work. This includes costs on direct labor, materials, equipment, facilities, services, information technology, contingency reserves, and indirect costs. Cost estimates for each activity are added together to create an overall cost estimate for the work package.
Basis of Estimates?
The basis of estimates involves supporting and additional information needed to justify cost estimates. Details can include the project scope, justification for the estimate, assumptions, constraints, confidence level on the estimate, and expected range of estimates.
Analogous estimating advantage and disadvantage?
Advantage:
Ensures that no work is inadvertently omitted from work
estimates
Disadvantage:
Can be sometimes difficult for less experienced managers to apportion cost estimates.
Bottom-up estimating advantage and disadvantage?
Advantage:
Accurate and gives lower level managers more responsibility.
Disadvantage:
Might be time consuming and can be used only after the WBS has been well-defined.
Parametric estimating advantage and disadvantage?
Advantage:
Not time consuming.
Disadvantage:
Might be inaccurate, depending on
the integrity of the historical
information used.
Cost Baseline?
Is a time-phased budget that will monitor and measure cost performance throughout the project life cycle. It is developed by adding the estimated costs of project
components by period. The cost baseline typically includes a budget contingency to accommodate the risk of incurring unidentifiable, but normally occurring costs, within the defined scope.